1. Ar10am and water
2. Told aloff 4.30am found cause
3. Spade off 3rd batch smelly cpoo
4. Put cdeter in two places
5. Watch see two blackie fighting
6. Lv11am
Sunday, August 14, 2011
Saturday, August 13, 2011
D138 1 grass crazy
1. Arard11am
2. Hot sun did 11.5 pavers near gate
3. Beewax 2 tables 1 footstepper
4. Early dinner break walk fm 14
5. Thunderstorm emergency light on
6. Another 20 pavers done in rain under porch
7. Bundled up 2nd batch cpoo
8. Near dark 4 pavers near gate done
9. Lv8pm
Next day told ard4.30am alwentoff loose vib
2. Hot sun did 11.5 pavers near gate
3. Beewax 2 tables 1 footstepper
4. Early dinner break walk fm 14
5. Thunderstorm emergency light on
6. Another 20 pavers done in rain under porch
7. Bundled up 2nd batch cpoo
8. Near dark 4 pavers near gate done
9. Lv8pm
Next day told ard4.30am alwentoff loose vib
Friday, August 12, 2011
Thursday, August 11, 2011
Wednesday, August 10, 2011
Tuesday, August 9, 2011
D134 Pye dampshield
1. Add 12 to the 18 pavers of grass making a total of 30
2. Apply pye dampshield to orin cement countertop and wet kitchen countertop
3. Slept at 10.30pm
2. Apply pye dampshield to orin cement countertop and wet kitchen countertop
3. Slept at 10.30pm
Monday, August 8, 2011
Sunday, August 7, 2011
D132 pearl grass
Visit: 1
5pm - 7.30pm
1. Plant a few pavers (10?) with pearl grass (10 sheets 1'x2')
2. one shower
5pm - 7.30pm
1. Plant a few pavers (10?) with pearl grass (10 sheets 1'x2')
2. one shower
Saturday, August 6, 2011
Friday, August 5, 2011
D130 2 tables up
2nd overnight
1. Set up 2 tables (one morning, one night)
2. Set up stand alone sink
3. Emerald curtain folded and c 2 net hanger rack up.
4. 2nd overnight.
1. Set up 2 tables (one morning, one night)
2. Set up stand alone sink
3. Emerald curtain folded and c 2 net hanger rack up.
4. 2nd overnight.
Thursday, August 4, 2011
Wdy 100 (d129) Last work day armed
Drizzling in the afternoon and then raining quite heavily ?4-5.30pm?
7.40am to 1st overnight.
1. 3+1 men to connect up the a-c-system.
2. Break for lunch at 12-1pm
3. Finished at around 3.30pm and tested
4. We went for early dinner at around 4-5pm (raining)
5. 2 Deliveries at 1.15pm, one after the other.
6. 1st overnight.
7.40am to 1st overnight.
1. 3+1 men to connect up the a-c-system.
2. Break for lunch at 12-1pm
3. Finished at around 3.30pm and tested
4. We went for early dinner at around 4-5pm (raining)
5. 2 Deliveries at 1.15pm, one after the other.
6. 1st overnight.
Wednesday, August 3, 2011
Wdy 99 (d128) Last painting
Drizzling 3pm-5pm
Visit: 2
7.4am - 11.15am
1. Touch up painting
2. Front 3 feet painting and 2 septic tank covers
3. Driver went here, blkg, bdrput, here
12.30pm - 4pm
1. Just waiting
Visit: 2
7.4am - 11.15am
1. Touch up painting
2. Front 3 feet painting and 2 septic tank covers
3. Driver went here, blkg, bdrput, here
12.30pm - 4pm
1. Just waiting
Tuesday, August 2, 2011
D127 we working
No rain
Visit: 1
11am-4pm
1. Drill and install curtains wire
2. Clean windows after removal
3. Put up temporary curtains
Visit: 1
11am-4pm
1. Drill and install curtains wire
2. Clean windows after removal
3. Put up temporary curtains
Monday, August 1, 2011
D126 Passing by
No rain
Visit: 1
4.30pm passed by in front and removed mydin leaflet from letter box.
Visit: 1
4.30pm passed by in front and removed mydin leaflet from letter box.
Sunday, July 31, 2011
D125 Halo come visiting
Drizzling ~9am to 10am
Visit:1
~10.30am to 1.45pm
- Rest and relax
- 1 visitor at 1pm
Visit:1
~10.30am to 1.45pm
- Rest and relax
- 1 visitor at 1pm
Saturday, July 30, 2011
Wdy 98 (d124) Wire mesh grill done
Raining heavily 8am - 10am
Visit: 2
1. 8am-2pm
- touch up gate grey and back grill grey
- put in the wire mesh grill (looks good as per design)
2. 9.45pm
- just pass by to view the lighting (took photos)
Visit: 2
1. 8am-2pm
- touch up gate grey and back grill grey
- put in the wire mesh grill (looks good as per design)
2. 9.45pm
- just pass by to view the lighting (took photos)
Friday, July 29, 2011
D123 11 to 8
Raining 5am? - 9am
Visit: 1 (11am to 8pm)
*List is not comprehensive*
1. Sweep floor
2. Mop mbr floor
3. Wipe shower wall tiles
4. Wash hand basin
5. Most importantly to observe the lights through tofu grilled at night
Visit: 1 (11am to 8pm)
*List is not comprehensive*
1. Sweep floor
2. Mop mbr floor
3. Wipe shower wall tiles
4. Wash hand basin
5. Most importantly to observe the lights through tofu grilled at night
Thursday, July 28, 2011
Wdy 97 (d122) Vent block done, ac
No rain
Visit: whole day (7.45am to 5pm)
1. Ac installed 10-12 1850
2. Vent block wall done
3. 3 tebu x 1.8
Visit: whole day (7.45am to 5pm)
1. Ac installed 10-12 1850
2. Vent block wall done
3. 3 tebu x 1.8
Wednesday, July 27, 2011
Wdy 96 (d121) Vent block
Rain: drizzle 2pm-4pm?
Visit: whole day 7.45am - 5.30pm
1. Putting in the vent block wall by W and AK
17 bricks x height 14 bricks (today did till 8 bricks height)
Visit: whole day 7.45am - 5.30pm
1. Putting in the vent block wall by W and AK
17 bricks x height 14 bricks (today did till 8 bricks height)
Tuesday, July 26, 2011
D120 Door stoppers
No rain
Visit: 1
~3.30pm to 4.45pm
1. Stick back npaper to mbdwdw
2. Put a screw on 2 door stoppers with hook (11 each)
3. Remove a little more dfsh
Visit: 1
~3.30pm to 4.45pm
1. Stick back npaper to mbdwdw
2. Put a screw on 2 door stoppers with hook (11 each)
3. Remove a little more dfsh
Monday, July 25, 2011
D119 Polish frank
No rain
Visit: 1
3.50pm-4.30pm (40mins - before early dinner)
1. Nap
2. Polish frank
3. Scoop up dfsh
Visit: 1
3.50pm-4.30pm (40mins - before early dinner)
1. Nap
2. Polish frank
3. Scoop up dfsh
Sunday, July 24, 2011
D118 Clean frank
Slight drizzle while we were there.
Visit: 1
11am-1.30pm (2.5hrs)
1. Sudoku medium hit snag
2. Scoop up more dfsh
3. Clean the frank
Visit: 1
11am-1.30pm (2.5hrs)
1. Sudoku medium hit snag
2. Scoop up more dfsh
3. Clean the frank
Saturday, July 23, 2011
D117 Keladi bunting
No rain
Visit: 1
9.30am-10.30am (1hr)
1. Scoop up the floating and sinking fsh.
2. Put in keladi bunting
3. Put in a turf of tiny leaves patch.
Visit: 1
9.30am-10.30am (1hr)
1. Scoop up the floating and sinking fsh.
2. Put in keladi bunting
3. Put in a turf of tiny leaves patch.
Friday, July 22, 2011
D116 Drained fishes
No rain
Visit: 1
11.30am - 3.30pm
1. Wipe lourve glass
2. Wipe wet kitchen floor trap
3. Put in dfish (2)
Visit: 1
11.30am - 3.30pm
1. Wipe lourve glass
2. Wipe wet kitchen floor trap
3. Put in dfish (2)
Thursday, July 21, 2011
Wednesday, July 20, 2011
D114 Stops 2
No rain
Visit: 2
8.15am-9.20am
1. Wipe floor trap with brasso
4pm-4.50pm
1. Air the place
Visit: 2
8.15am-9.20am
1. Wipe floor trap with brasso
4pm-4.50pm
1. Air the place
Tuesday, July 19, 2011
Monday, July 18, 2011
Wdy 95 (d112) assortment work
No rain
Visit: 2
8am-11.15am
1. C came with 2 men to cut the drainage passage for the folding door and put in the 2 septic tanks covers.
2. Alpha service man exchange the hose (said the no hole one is a dummy set) and put in a new screw to fasten the cover.
1pm-3.45pm
1. Vin Art 2 men tore off the wrongly pasted sheet and put in a new one on the outer (right side)
2. Left the plastic? ridges for us to put in ourselves when the door is dried
3. Asked for lighter (dunno why) - later they went out and bought one.
*16 is back finally from M after visiting her dai kor.
Visit: 2
8am-11.15am
1. C came with 2 men to cut the drainage passage for the folding door and put in the 2 septic tanks covers.
2. Alpha service man exchange the hose (said the no hole one is a dummy set) and put in a new screw to fasten the cover.
1pm-3.45pm
1. Vin Art 2 men tore off the wrongly pasted sheet and put in a new one on the outer (right side)
2. Left the plastic? ridges for us to put in ourselves when the door is dried
3. Asked for lighter (dunno why) - later they went out and bought one.
*16 is back finally from M after visiting her dai kor.
Sunday, July 17, 2011
Saturday, July 16, 2011
D110 1st night visit
No rain
Visit: 2
1. Around 1030am to turn off the vent fans.
2. Around 8.45pm to see how the lights look like in the dark.
Visit: 2
1. Around 1030am to turn off the vent fans.
2. Around 8.45pm to see how the lights look like in the dark.
Friday, July 15, 2011
Wdy 94 (d109) Painters touch up 1-2 hours
Raining since wee hours.
Visit: 1
8am-1030am
1. 2 painters touch up paint here and there. Left at 1030 followed by us. C couldn't make it.
Visit: 1
8am-1030am
1. 2 painters touch up paint here and there. Left at 1030 followed by us. C couldn't make it.
Thursday, July 14, 2011
Wdy 93 (d108) Sweep, mop, varnish whole floor
No rain?
Visit: 1 (whole day for one)
1. 2 painters sweep, mop and varnish the floors of the whole house. So quick. They left at about 1630.
2. 1030-1600 not around left for meetup execs.
Visit: 1 (whole day for one)
1. 2 painters sweep, mop and varnish the floors of the whole house. So quick. They left at about 1630.
2. 1030-1600 not around left for meetup execs.
Wednesday, July 13, 2011
D107 Rest day by us
No rain - hazy
Visit 1
4.30pm - 5.15pm
1. Water the sand
2. Put in abate (day 2 of soaking)
3. Remove boxes and plastic bags
4. Wipe debris off lower sockets
Visit 1
4.30pm - 5.15pm
1. Water the sand
2. Put in abate (day 2 of soaking)
3. Remove boxes and plastic bags
4. Wipe debris off lower sockets
Tuesday, July 12, 2011
Wdy 92 (d106) Touchup, glass doors
No rain
Visit: whole day (9.30am to 4.30pm)
1. Got call from painter asking us to go there at 9 so reach there 9.30am
2. One eman finish up the work, putting up 2 lights front 3 feet, put on two eplugs for back 2 vent fans, connect the shower, change front porch lights to yellow and remove cover.
3. Vin art came to install 2 glass doors for the 2 cubicles.
4. No water coming out from shower so called plumber who came and discover the shower hose is faulty no hole in it.
5. Called C to pick up the scaffolding and he sent W to pick it up about 20? 30? mins from our call
6. Painter clean up the sec doors frame
**** Work on 18 - Man came to do something to the drain so the water from 19 does not flow onto the driveway.
- Painter sweep and varnish the pebblewash
Visit: whole day (9.30am to 4.30pm)
1. Got call from painter asking us to go there at 9 so reach there 9.30am
2. One eman finish up the work, putting up 2 lights front 3 feet, put on two eplugs for back 2 vent fans, connect the shower, change front porch lights to yellow and remove cover.
3. Vin art came to install 2 glass doors for the 2 cubicles.
4. No water coming out from shower so called plumber who came and discover the shower hose is faulty no hole in it.
5. Called C to pick up the scaffolding and he sent W to pick it up about 20? 30? mins from our call
6. Painter clean up the sec doors frame
**** Work on 18 - Man came to do something to the drain so the water from 19 does not flow onto the driveway.
- Painter sweep and varnish the pebblewash
Monday, July 11, 2011
Wdy 91 (d105) Vent fan shower wfill
No rain
Visit: whole day
1015am
1. Both emen at site when we arrived with C after getting the frightcall.
2. Back to get all things
3. wash tank away 250gallons wtr
4. Big and small in
5. Manage to get small into 103cm (after requesting and changing my request)
6. Pman connected shower, 3 taps and 1 bottle trap
7. Lights almost done
8. All 3 parties got the forms
Visit: whole day
1015am
1. Both emen at site when we arrived with C after getting the frightcall.
2. Back to get all things
3. wash tank away 250gallons wtr
4. Big and small in
5. Manage to get small into 103cm (after requesting and changing my request)
6. Pman connected shower, 3 taps and 1 bottle trap
7. Lights almost done
8. All 3 parties got the forms
Sunday, July 10, 2011
D104 Checkup after rain
Rain: 11am - 3pm
Visit: 1
~4.30pm
1. Went in to look at the effect of rain
2. Water through the folding door
3. Water line on the pavers sand
Visit: 1
~4.30pm
1. Went in to look at the effect of rain
2. Water through the folding door
3. Water line on the pavers sand
Saturday, July 9, 2011
D103 Night lights
Backdated - post date: Sunday 10 July 2011
No rain
Visit: 2
10.20am - 11am
1. Got forms from pplhky
2. pplhky took photos
~8.30pm
1. Took photos of front and back lights on
No rain
Visit: 2
10.20am - 11am
1. Got forms from pplhky
2. pplhky took photos
~8.30pm
1. Took photos of front and back lights on
Friday, July 8, 2011
Wdy 90 (d102) Autoarm, lights
Backdated - post date: Sunday 10 July 2011
Intermittent drizzle
Visit: 2 (actually whole day we were onsite except for 1 break to str)
8.20am - 2pm
1. 2 painters were waiting
2. Touch up and painted gate pillars tungsten (a tinge of grey only)
3. OmL paint pink
4. 1 eman put in lights
5. Bmmg close up the ends of metal roof truss - can't do anything about the part cut by plumber
3pm - 5pm
1. Painters remove all their things
2. Metal cover back door in
Intermittent drizzle
Visit: 2 (actually whole day we were onsite except for 1 break to str)
8.20am - 2pm
1. 2 painters were waiting
2. Touch up and painted gate pillars tungsten (a tinge of grey only)
3. OmL paint pink
4. 1 eman put in lights
5. Bmmg close up the ends of metal roof truss - can't do anything about the part cut by plumber
3pm - 5pm
1. Painters remove all their things
2. Metal cover back door in
Thursday, July 7, 2011
Wdy 89 (d101) Last wetworks day
Backdated - post date: Sunday 10 July 2011
Cloudy
Visit: 2
7.55am - 1pm
1. Touching up plastering here and there
2. Token appreciation 50x2
3. Painters at work - black downpipes
4. 2 Eman at work
5. Decide to paint the cement rendered front fencing tungsten grey
3pm-5pm
1. Gate, back window grilles and trashchute door
Cloudy
Visit: 2
7.55am - 1pm
1. Touching up plastering here and there
2. Token appreciation 50x2
3. Painters at work - black downpipes
4. 2 Eman at work
5. Decide to paint the cement rendered front fencing tungsten grey
3pm-5pm
1. Gate, back window grilles and trashchute door
Wednesday, July 6, 2011
Wdy 88 (d100) Doors in
Backdated - post date: Sunday 10 July 2011
Bits of rain
Visit: 3
7.45am - 10am
1. 2 men came and installed the doors and door knobs and fascia board (18) - signs of termites
2. AK and Y plastered up the external gate arms
3. AK put in red bricks for external front walkway
4. Emen relay w
11am - 1 pm
1. Door block not suitable to be installed
3.30pm - 5pm
1. Bboy came and helped move unrequired things onto lorry
*** pebble driveway was washed with acid today
Bits of rain
Visit: 3
7.45am - 10am
1. 2 men came and installed the doors and door knobs and fascia board (18) - signs of termites
2. AK and Y plastered up the external gate arms
3. AK put in red bricks for external front walkway
4. Emen relay w
11am - 1 pm
1. Door block not suitable to be installed
3.30pm - 5pm
1. Bboy came and helped move unrequired things onto lorry
*** pebble driveway was washed with acid today
Tuesday, July 5, 2011
Wdy 87 (d99) wgone wc in
Backdated - post date: Sunday 10 July 2011
No rain
Visit: 1 (8am - 6pm)
1. Brought the toilet bowl and taps
2. Discover
- percussion hammer gone
- 2 septic tank covers gone
- wgone
3. One e-man came to ensure 1 point has e for usage
4. Toilet bowl and internal taps and bottle trap in
5. Fast unpainted grilles in at 5pm
6. C brought 3 doors in
It is the effort mourned
*** Y, AK and bboy only worked on 18 pebble wash putting in the cement mix with pebbles and then wash the cement away
No rain
Visit: 1 (8am - 6pm)
1. Brought the toilet bowl and taps
2. Discover
- percussion hammer gone
- 2 septic tank covers gone
- wgone
3. One e-man came to ensure 1 point has e for usage
4. Toilet bowl and internal taps and bottle trap in
5. Fast unpainted grilles in at 5pm
6. C brought 3 doors in
It is the effort mourned
*** Y, AK and bboy only worked on 18 pebble wash putting in the cement mix with pebbles and then wash the cement away
Monday, July 4, 2011
Wdy 86 (d98) Water tank connected
Backdated - post date: Sunday 10 July 2011
No rain
Visit: 2 (at ef3oh)
8am - 1pm
1. Waiting with the taps but soon see that tap work will not be today so left for lunch.
2. was told that tinman quit
3. Pipe work only
4. Glass folding door men came to look at fixing the gap and the bottom part that scratches the floor.
5pm
1. Noticed that the w-meter was moved and the elbow was encased in concrete so we removed the concrete.
*** Don't think any wet work was done on the place as both men were working on the concrete for 18 driveway
No rain
Visit: 2 (at ef3oh)
8am - 1pm
1. Waiting with the taps but soon see that tap work will not be today so left for lunch.
2. was told that tinman quit
3. Pipe work only
4. Glass folding door men came to look at fixing the gap and the bottom part that scratches the floor.
5pm
1. Noticed that the w-meter was moved and the elbow was encased in concrete so we removed the concrete.
*** Don't think any wet work was done on the place as both men were working on the concrete for 18 driveway
Sunday, July 3, 2011
Wdy 85 (d97) Clean up
Backdated - post date: Sunday 10 July 2011
No rain
Visit: 2 (at ef3oh)
10.30am?
1. Pipe work
2. C's son and sman "clean" the floor - remove everything from the floor of the house, sweep and wash the floor.
5pm?
1. C's son (new red car bka) and sman waiting outside the house for lorry to remove more things.
*** Sman use the percussion hammer to hack the whole of 18 concrete driveway and lorry AC removed the debris
No rain
Visit: 2 (at ef3oh)
10.30am?
1. Pipe work
2. C's son and sman "clean" the floor - remove everything from the floor of the house, sweep and wash the floor.
5pm?
1. C's son (new red car bka) and sman waiting outside the house for lorry to remove more things.
*** Sman use the percussion hammer to hack the whole of 18 concrete driveway and lorry AC removed the debris
Saturday, July 2, 2011
Wdy 84 (d96) Concrete front driveway done
Backdated - post date: Sunday 10 July 2011
No rain
Visit 2 (at ef3oh)
8.30am - 11am
1. One watch marathon, one went look see
2. Folding door top large gap
3. Tinman MIA so only 2 fifties Y and AK
12noon
1. Visit metal works workshop to see gate. No need middle bar.
5pm
1. Concrete front part of driveway done
2. E-meter moved to front wall
3. Pipe work on fencewall near 18 done with gap for wtrfltr
*** No work done on 18 driveway. Only half of the driveway has its top layer of concrete removed
No rain
Visit 2 (at ef3oh)
8.30am - 11am
1. One watch marathon, one went look see
2. Folding door top large gap
3. Tinman MIA so only 2 fifties Y and AK
12noon
1. Visit metal works workshop to see gate. No need middle bar.
5pm
1. Concrete front part of driveway done
2. E-meter moved to front wall
3. Pipe work on fencewall near 18 done with gap for wtrfltr
*** No work done on 18 driveway. Only half of the driveway has its top layer of concrete removed
Friday, July 1, 2011
Wdy 83 (d95) Folding door in
Backdated - post date: Sunday 10 July 2011
No rain
Visit: 1 (8am-10.30am)
1. Pavers for driveway
2. E men putting in switches and etc
3. A men continue laying ducting
4. Drain covered with concrete slabs
5. Install folding door and put in glass for the louvers windows
*** Tinman was tasked to use the e-cutter to cut a line between 18 tiled driveway and 18 concrete driveway in order to do the pebble wash and then break the concrete driveway.
No rain
Visit: 1 (8am-10.30am)
1. Pavers for driveway
2. E men putting in switches and etc
3. A men continue laying ducting
4. Drain covered with concrete slabs
5. Install folding door and put in glass for the louvers windows
*** Tinman was tasked to use the e-cutter to cut a line between 18 tiled driveway and 18 concrete driveway in order to do the pebble wash and then break the concrete driveway.
Thursday, June 30, 2011
Wdy 82 (d94) Fans up bar in
Rain: nil
Visit: 2
Did not meet C today
8am - 9am
1. SS middle bar has been done
2. pavers still doing
3.50pm-4.30pm
1. 2 fans are up
2. 16 sepia light balls done
3. gate roller bar in
4. side drain casting
5. house number done - nice
6. cast drain covers
Visit: 2
Did not meet C today
8am - 9am
1. SS middle bar has been done
2. pavers still doing
3.50pm-4.30pm
1. 2 fans are up
2. 16 sepia light balls done
3. gate roller bar in
4. side drain casting
5. house number done - nice
6. cast drain covers
Wednesday, June 29, 2011
Wdy 81 (d93) Pavers
Rain: 9am -11am
Visit: 2
8am
1. Started to rain a little while after we arrived
2. Putting in the letters
3. compacting the sand
4. Painting 18 house
5. A+C people suddenly turned up and started doing snaking ducting
6. Move emeter and do fuse box
7. Plastering up the nail tiny holes (impurities)
8. Do wash feet place.
9. Saw the 1st tank (inspection tank) - all exposed - definitely smell can float up.
12 noon
1. Start putting in the pavers
2. Compacting machine is taken away
3. Started doing drain cover slabs
4. Complete plastering gate column nr 18
Visit: 2
8am
1. Started to rain a little while after we arrived
2. Putting in the letters
3. compacting the sand
4. Painting 18 house
5. A+C people suddenly turned up and started doing snaking ducting
6. Move emeter and do fuse box
7. Plastering up the nail tiny holes (impurities)
8. Do wash feet place.
9. Saw the 1st tank (inspection tank) - all exposed - definitely smell can float up.
12 noon
1. Start putting in the pavers
2. Compacting machine is taken away
3. Started doing drain cover slabs
4. Complete plastering gate column nr 18
Tuesday, June 28, 2011
Wdy 80 (d92) Assortment work
Rain: nil
Visit:2
8-11.30am
1. Waited for C to talk about solving the water seepage.
2. Fixing the 17 18 gap flow
3. Plastering concrete tank, basin in front
4. Doing the raised up for the back kitchen counter.
5. Emen pulling more wires
6. Youngmen helped out a bit
7. 18 wm moved.
8. Lorry collect waste
4-4.30pm
1. AK went up to roof to solve water seepage
2. cap over mail opening
Visit:2
8-11.30am
1. Waited for C to talk about solving the water seepage.
2. Fixing the 17 18 gap flow
3. Plastering concrete tank, basin in front
4. Doing the raised up for the back kitchen counter.
5. Emen pulling more wires
6. Youngmen helped out a bit
7. 18 wm moved.
8. Lorry collect waste
4-4.30pm
1. AK went up to roof to solve water seepage
2. cap over mail opening
Monday, June 27, 2011
Wdy 79 (d91) Raining can't work
Rain: heavily 3am - 10am (mostly heavy, drizzling for some intervals and then stopped at 10am)
Visit: 1
7.40am
1. Went direct there, observed rain patterns
2. Use nail and hammer to chip away the impurities drawn out by the paint
3. Got the letters, working on it with a ?penknife?
4. 17 18 one gap gushing water into wash basin
5. mystery paver arranger revealed
6. Use slab to cover drain
7. Pmen doing some work
Visit: 1
7.40am
1. Went direct there, observed rain patterns
2. Use nail and hammer to chip away the impurities drawn out by the paint
3. Got the letters, working on it with a ?penknife?
4. 17 18 one gap gushing water into wash basin
5. mystery paver arranger revealed
6. Use slab to cover drain
7. Pmen doing some work
Sunday, June 26, 2011
Wdy 78 (d90) E and P men
Rain: 2-2.30pm. 4-5pm
Visit: 2
11.30am
- try out the glights
- emen doing plastering themselves
- emen doing some wiring work
- saga security services?
5pm
- just a little more pipe gets done
- hole is discovered
- someone arranged the pavers to be vent block - but who?
- corner tour free advice
- secret garden
Visit: 2
11.30am
- try out the glights
- emen doing plastering themselves
- emen doing some wiring work
- saga security services?
5pm
- just a little more pipe gets done
- hole is discovered
- someone arranged the pavers to be vent block - but who?
- corner tour free advice
- secret garden
Saturday, June 25, 2011
Wdy 77 (d89) Parking stopper
Rain: nil
Visit: 2 (Didnot see C today).
1. 8.30am
- Mini courtyard grill done (but missing the middle long bar so got to add it).
- Plastering the top cement bar of the red brick fence nicely.
- Measuring the level of the next 1.x? feet ground.
- Tinman mixing cement
2. 4.55pm
- AK and plumber leaving
- no red flowers/wheels, only 3 blue sticks
- 3 door frames painted black
- Parking bar stopper done
- cement layed for the next 1.x? feet before stopper
- sand readied for pavers
- wiring to gate done
- the slanting big small folding glass door footing rectified
- saw a man cutting off some parts of the mango tree
Visit: 2 (Didnot see C today).
1. 8.30am
- Mini courtyard grill done (but missing the middle long bar so got to add it).
- Plastering the top cement bar of the red brick fence nicely.
- Measuring the level of the next 1.x? feet ground.
- Tinman mixing cement
2. 4.55pm
- AK and plumber leaving
- no red flowers/wheels, only 3 blue sticks
- 3 door frames painted black
- Parking bar stopper done
- cement layed for the next 1.x? feet before stopper
- sand readied for pavers
- wiring to gate done
- the slanting big small folding glass door footing rectified
- saw a man cutting off some parts of the mango tree
Friday, June 24, 2011
Wdy 76 (d88) cont' brick fence
Rain: nil
Visit: 1
8am - 9.30am
1. AK continues with brick fence work
2. Bumblebee continues with concrete fish container
3. Y do wet room basin which we brought
4. 2 painters still doing touching up
5. Welectrician brought new helper do wiring with MegaKabel
6. Got lights 4x15 2x35 and replacement lights 2x12
7. Changed glights
8. Got one more eng red tap
Visit: 1
8am - 9.30am
1. AK continues with brick fence work
2. Bumblebee continues with concrete fish container
3. Y do wet room basin which we brought
4. 2 painters still doing touching up
5. Welectrician brought new helper do wiring with MegaKabel
6. Got lights 4x15 2x35 and replacement lights 2x12
7. Changed glights
8. Got one more eng red tap
Thursday, June 23, 2011
Wdy 75 (d87) brick fence
Rain: nil
Visit: 2
8.20am-11am
1. Explain brickwork fence design
2. Window guys fix glass and folding door frame
3. 2 painters continue painting work
1.30pm-5.30pm
1. continue brickwork fence - remove plaster line and redo
2. Window guys left at 2.30pm - fixed back and front windows, fixed glass, frames for door and lourve windows courtyard.
3. Plumber wants to move the red flower design downwards.
4. Informed plumber about the filter and he said he will do pvc pipe portion for them to remove it easily without me prompting him to do a pvc section.
5. Asked plumber about the pipe joint which is not ss and he said it is copper because no threading on the cut main pipe so can't use ss joint - I believe it is just a brass joint because it does not look like copper to me (not red enough).
6. Iced tea 1.9 for all 7 - 4 regulars, 1 plumber, 2 painters
7. Kitchen ss sink embedded into the concrete kitchen counter
8. Skip removed and parked on the main side road
Visit: 2
8.20am-11am
1. Explain brickwork fence design
2. Window guys fix glass and folding door frame
3. 2 painters continue painting work
1.30pm-5.30pm
1. continue brickwork fence - remove plaster line and redo
2. Window guys left at 2.30pm - fixed back and front windows, fixed glass, frames for door and lourve windows courtyard.
3. Plumber wants to move the red flower design downwards.
4. Informed plumber about the filter and he said he will do pvc pipe portion for them to remove it easily without me prompting him to do a pvc section.
5. Asked plumber about the pipe joint which is not ss and he said it is copper because no threading on the cut main pipe so can't use ss joint - I believe it is just a brass joint because it does not look like copper to me (not red enough).
6. Iced tea 1.9 for all 7 - 4 regulars, 1 plumber, 2 painters
7. Kitchen ss sink embedded into the concrete kitchen counter
8. Skip removed and parked on the main side road
Wednesday, June 22, 2011
Wdy 74 (d86) shoe cbench
Rain: a few droplets around 3pm
Visit: 2
7.50am-10am
1. Sauna ka
2. C did not visit in this time frame
3. Passed letterings to AK
4. Full skip still there
5. Was told about newspapers andp
6. L talked about expaint
7. From photos can see that:
- Sunflower white looks yellow in sun and very pale yellow in shade
- Sunflower white on outside wall and back wall
- Painting continues
- Wet kit and wet area concrete counter top done
- Doing seat and outside wash basin
- Gate pillars, wmeter and thrash chute done
- New bricks arrived for fence
- Tinman in the morning but not in the afternoon
- All skylights done
3pm-3.50pm
1. Wash mop concrete raised edge done
2. Ask atpis people when is the time to get the bfree installed - they recommend after everything is completed and done so it was decided bym and agreed bytlc that to let plumber all everything in ss then only atpis people come to disconnect necessary parts to connect and put in the atpis.
3. Noticed that the first joint is not ss will have to ask about this tomorrow
Visit: 2
7.50am-10am
1. Sauna ka
2. C did not visit in this time frame
3. Passed letterings to AK
4. Full skip still there
5. Was told about newspapers andp
6. L talked about expaint
7. From photos can see that:
- Sunflower white looks yellow in sun and very pale yellow in shade
- Sunflower white on outside wall and back wall
- Painting continues
- Wet kit and wet area concrete counter top done
- Doing seat and outside wash basin
- Gate pillars, wmeter and thrash chute done
- New bricks arrived for fence
- Tinman in the morning but not in the afternoon
- All skylights done
3pm-3.50pm
1. Wash mop concrete raised edge done
2. Ask atpis people when is the time to get the bfree installed - they recommend after everything is completed and done so it was decided bym and agreed bytlc that to let plumber all everything in ss then only atpis people come to disconnect necessary parts to connect and put in the atpis.
3. Noticed that the first joint is not ss will have to ask about this tomorrow
Tuesday, June 21, 2011
Wdy 73 (d85) wet kit counter
Rain: nil
Visit: 1
8.15am
1. Left house at 7.30am but due to the horrendous traffic, reached there at 8.15am
2. Was told that:
- W was there to supervise M to do all the concrete built-ins, starting with wet kit counter
- An error was spotted for the wet area counter measurement 22' from wall and the bottom is 22' from tile whereas the bottom should be 22' from wall as well - was rectified
- The gate pillars are up
- The water meter house and the trash chute have also taken form in bricks
- Water meter has been moved and all the black pipes are replaced by ss pipes
- Y started doing bricks for the rest of the fence but was stopped by C because the brick pattern is different and the design is with AK
- Tinman broke 16 gate light while breaking the previous near 16 pillar to be shorter (they should have done this earlier when I confirmed with C that the pillar is supposed to be shorter.
- Was shown a wooden cut outs of the letters which are not according to spec at all so was rejected and the specs will be given again tomorrow.
- Painters are onsite and paint cans are there as well.
- Front wall has been white washed and the e-mains wiring has been put back to that wall
- Wet area floor is fully tiled now.
- The button to press ding dong has been installed on the left gate pillar
Visit: 1
8.15am
1. Left house at 7.30am but due to the horrendous traffic, reached there at 8.15am
2. Was told that:
- W was there to supervise M to do all the concrete built-ins, starting with wet kit counter
- An error was spotted for the wet area counter measurement 22' from wall and the bottom is 22' from tile whereas the bottom should be 22' from wall as well - was rectified
- The gate pillars are up
- The water meter house and the trash chute have also taken form in bricks
- Water meter has been moved and all the black pipes are replaced by ss pipes
- Y started doing bricks for the rest of the fence but was stopped by C because the brick pattern is different and the design is with AK
- Tinman broke 16 gate light while breaking the previous near 16 pillar to be shorter (they should have done this earlier when I confirmed with C that the pillar is supposed to be shorter.
- Was shown a wooden cut outs of the letters which are not according to spec at all so was rejected and the specs will be given again tomorrow.
- Painters are onsite and paint cans are there as well.
- Front wall has been white washed and the e-mains wiring has been put back to that wall
- Wet area floor is fully tiled now.
- The button to press ding dong has been installed on the left gate pillar
Monday, June 20, 2011
Wdy 72 (d84) Gate pillars
Rain: nil
Visit: 1
9.15am - 1030am
1. C is already there when we got there since we informed him this morning we will be there at 9am after getting the taps - 2 pillar @ 112 (rrp 160 - previously quoted 91), 1 bib and 3 bib hose @ 62 (rrp 88 - previously quoted 55).
2. Also got a pop waste 39 and a bottle trap 35
3. Went over the sizes of thrash room, wm area, extra bricks area.
4. Went over design of wet area counter and wet kitchen counter.
5. Show the wash basin and kitchen sink.
6. Point out the paint we have chosen from the catalogue.
7. C will ask W to do all the concrete built-ins.
8. Activities on site:
- Break up the near the drain stones to do the gate pillar
- remove more dirt in the garden to make way for concrete before putting in pavers
- start work on building the gate pillars
- painters sanding the bottom white wash paint to paint the real thing
- eman furiously digging for the pipe conduit that they put in earlier in the ground
Visit: 1
9.15am - 1030am
1. C is already there when we got there since we informed him this morning we will be there at 9am after getting the taps - 2 pillar @ 112 (rrp 160 - previously quoted 91), 1 bib and 3 bib hose @ 62 (rrp 88 - previously quoted 55).
2. Also got a pop waste 39 and a bottle trap 35
3. Went over the sizes of thrash room, wm area, extra bricks area.
4. Went over design of wet area counter and wet kitchen counter.
5. Show the wash basin and kitchen sink.
6. Point out the paint we have chosen from the catalogue.
7. C will ask W to do all the concrete built-ins.
8. Activities on site:
- Break up the near the drain stones to do the gate pillar
- remove more dirt in the garden to make way for concrete before putting in pavers
- start work on building the gate pillars
- painters sanding the bottom white wash paint to paint the real thing
- eman furiously digging for the pipe conduit that they put in earlier in the ground
Sunday, June 19, 2011
D83 rest day
Rain: droplets
Visit: 1
11.15am - 12.15
1. Both sides fence 16, 18 has been plastered.
2. Steel lintel put up looks so thick 3" x 3"
3. Both sides brick walls back plastered.
4. Bricks marked out the perimeter fencing boxes
5. Side roof tiles put on
6. Workers rest day
Visit: 1
11.15am - 12.15
1. Both sides fence 16, 18 has been plastered.
2. Steel lintel put up looks so thick 3" x 3"
3. Both sides brick walls back plastered.
4. Bricks marked out the perimeter fencing boxes
5. Side roof tiles put on
6. Workers rest day
Saturday, June 18, 2011
Wdy 71 (d82) fence near 16 plaster
Rain: a few droplets around 1.30pm
Visit: 2
8am-9am
1. C was already onsite
2. Went over design of concrete built-ins
3. Things done:
- wet area nearly fully tiled
- courtyard area floor done with 6 concrete slabs
- all floor traps inside house done
- 3 septic tanks cover done
- mini courtyard roof sides lined with metal sheet
4. Things today:
- side roof tiles brought up to roof
- cement mortar roof middle tiles while droplets of rain fell at 1.30pm
- plaster both side pillars
- break up and remove all existing concrete slab in garden
- drill deeper into fence wall near 16
- plaster near 16 side below white vases fence
- smoothen 18 side fence wall
- grill man came to measure to do lintel for folding door
11am-1.30pm
1. Went over ducting with emen
2. Waited for A to arrive at 12.30pm
3. Went over the process of CCC
Visit: 2
8am-9am
1. C was already onsite
2. Went over design of concrete built-ins
3. Things done:
- wet area nearly fully tiled
- courtyard area floor done with 6 concrete slabs
- all floor traps inside house done
- 3 septic tanks cover done
- mini courtyard roof sides lined with metal sheet
4. Things today:
- side roof tiles brought up to roof
- cement mortar roof middle tiles while droplets of rain fell at 1.30pm
- plaster both side pillars
- break up and remove all existing concrete slab in garden
- drill deeper into fence wall near 16
- plaster near 16 side below white vases fence
- smoothen 18 side fence wall
- grill man came to measure to do lintel for folding door
11am-1.30pm
1. Went over ducting with emen
2. Waited for A to arrive at 12.30pm
3. Went over the process of CCC
Friday, June 17, 2011
Wdy 70 (d81) Red brick ren floor
Rain: nil
Visit: 2
8am
1. The bottom side garden wall near to 18 has been fully plastered.
2. Down pipe has been put on the side near to 18.
3. 2 drainage pipes near 18 have been put into the ground all the way to the drain.
4. Wall tiles in 2 cubicles done half way (no more tiles - not enough)
5. Wc floor seems too low until the ventilation pipe is exposed horizontally but C says it can and will be fixed by making the floor high enough to cover the exposed pipe and then slant towards the outlet pipe - no issue at all.
6. Courtyard floor too low until the outlet pipe joint bend is exposed, pointed out to C who says it is ok can be covered by the concrete floor.
7. Decide on how the pipes leading to the wm is to be done - above ground.
8. To have a barrier or planter box protect the pipe.
9. Drain hole near 18 instead of in the middle.
10. Working on floor of wet kitchen.
11. Saw the ss frames for the 3 septic tanks.
12. A called around 4pm to say ok to meet tomorrow around 2-3pm or earlier - have to wait for his call.
2pm
1. Passed by saw C's cutting red bricks - think it is to do the ren floor.
2. Skip is full from the cement floor of the garden - hard but no iron rods.
3. Blue white barrier torn fabric has been removed.
4. Will be removing the notice board too in order to build the fencing.
Visit: 2
8am
1. The bottom side garden wall near to 18 has been fully plastered.
2. Down pipe has been put on the side near to 18.
3. 2 drainage pipes near 18 have been put into the ground all the way to the drain.
4. Wall tiles in 2 cubicles done half way (no more tiles - not enough)
5. Wc floor seems too low until the ventilation pipe is exposed horizontally but C says it can and will be fixed by making the floor high enough to cover the exposed pipe and then slant towards the outlet pipe - no issue at all.
6. Courtyard floor too low until the outlet pipe joint bend is exposed, pointed out to C who says it is ok can be covered by the concrete floor.
7. Decide on how the pipes leading to the wm is to be done - above ground.
8. To have a barrier or planter box protect the pipe.
9. Drain hole near 18 instead of in the middle.
10. Working on floor of wet kitchen.
11. Saw the ss frames for the 3 septic tanks.
12. A called around 4pm to say ok to meet tomorrow around 2-3pm or earlier - have to wait for his call.
2pm
1. Passed by saw C's cutting red bricks - think it is to do the ren floor.
2. Skip is full from the cement floor of the garden - hard but no iron rods.
3. Blue white barrier torn fabric has been removed.
4. Will be removing the notice board too in order to build the fencing.
Thursday, June 16, 2011
Wdy 69 (d80) Redo the eyes!
Rain: nil
Visit: 1
8am
1. Two sides red brick walls done with one brick near 18 wall orangey in colour so it was taken out and a redder brick put in.
2. The two pipe holes look like eyes according to someone so had to be taken out and just leave a brick gap.
3. All brick gate pillars are gone.
4. Skip 23 replaced with skip 6.
5. Courtyard floor being done.
6. Plumber came with C and was given the specifications of moving the wm.
7. Saw one tiler coming in to do the wet room tiles.
8. Text A to meet up this week onsite but no reply yet.
Visit: 1
8am
1. Two sides red brick walls done with one brick near 18 wall orangey in colour so it was taken out and a redder brick put in.
2. The two pipe holes look like eyes according to someone so had to be taken out and just leave a brick gap.
3. All brick gate pillars are gone.
4. Skip 23 replaced with skip 6.
5. Courtyard floor being done.
6. Plumber came with C and was given the specifications of moving the wm.
7. Saw one tiler coming in to do the wet room tiles.
8. Text A to meet up this week onsite but no reply yet.
Wednesday, June 15, 2011
Wdy 68 (d79) Breakdown gate pillars
Rain: thunder no rain
Visit: 1
7.55am
1. Saw that the gate and iron fence have been removed and locked to the new skip.
2. New skip no 23
3. The brick fence below the iron fence has been removed as well.
4. The gate brick pillar near to 16 is half down.
5. The gate brick pillar near to 18 is just touched a bit.
6. Told C about new design for vent block wall so bumblebee (near 18) and Y (near 16) started putting up the bricks one each side.
7. Sturdym working on the floor of the mini courtyard.
8. Thinman breaking down the gate brick pillar near 16 with the percussion hammer.
9. Bguy working somewhere inside the house.
10. Saiyuki was in to collect some of his things and dropped of bguy and left to go to some other site.
11. W dropped by to collect some things which are small that I could not see what they are when he left on his bike.
Visit: 1
7.55am
1. Saw that the gate and iron fence have been removed and locked to the new skip.
2. New skip no 23
3. The brick fence below the iron fence has been removed as well.
4. The gate brick pillar near to 16 is half down.
5. The gate brick pillar near to 18 is just touched a bit.
6. Told C about new design for vent block wall so bumblebee (near 18) and Y (near 16) started putting up the bricks one each side.
7. Sturdym working on the floor of the mini courtyard.
8. Thinman breaking down the gate brick pillar near 16 with the percussion hammer.
9. Bguy working somewhere inside the house.
10. Saiyuki was in to collect some of his things and dropped of bguy and left to go to some other site.
11. W dropped by to collect some things which are small that I could not see what they are when he left on his bike.
Tuesday, June 14, 2011
Wdy 67 (d78) Dismantle fence
Rain: drizzle 1015-1100
Visit: 1
8am-1015am
1. Waited until 9.30am for C
2. Some working on the floor
3. Others working on the front 3 feet - lintel issue for front grille (workaround fixed grille on top to be discussed tomorrow).
4. Spotted king kong back rc roof.
5. C asked to take back to office everything that is not needed and to retained a few roof tiles as spare on top of the back rc roof.
6. Called Y to talk about front vent blocks - must go later.
Visit: 1
8am-1015am
1. Waited until 9.30am for C
2. Some working on the floor
3. Others working on the front 3 feet - lintel issue for front grille (workaround fixed grille on top to be discussed tomorrow).
4. Spotted king kong back rc roof.
5. C asked to take back to office everything that is not needed and to retained a few roof tiles as spare on top of the back rc roof.
6. Called Y to talk about front vent blocks - must go later.
Monday, June 13, 2011
Wdy 66 (d77) Paint work starts
Rain: -
Visit: 1
10.15am
1. Painter with workers putting on skim coat in wet kitchen and also sealant in wet area.
2. Saiyuki working on MBR floor.
3. Y, Ak, Bumblebee, sturdym working on floor for front 3 feet - ground beam.
4. Tinm removing debris from within the house to the skip.
5. Same no.04 skip but with previous content emptied.
Visit: 1
10.15am
1. Painter with workers putting on skim coat in wet kitchen and also sealant in wet area.
2. Saiyuki working on MBR floor.
3. Y, Ak, Bumblebee, sturdym working on floor for front 3 feet - ground beam.
4. Tinm removing debris from within the house to the skip.
5. Same no.04 skip but with previous content emptied.
Sunday, June 12, 2011
Saturday, June 11, 2011
Wdy 65 (d75) Floor, walls, bricks
Rain: Heavy rain for ~1.5 hours ~4pm to 5.30pm?
Visit: 1
11.15am
1. Back e-ducting done outside. 19 skip was taken away but ss water tank moved to a temporary place on the roof.
2. Y working on MBR front wall.
3. Sturdym and saiyuki on plastering inner front dining wall.
4. AK working on wet area floor.
5. Bumblebee putting up bricks in courtyard.
6. Bguy cutting previous exposed iron rods in the floor.
7. Tinman mixing cement and sand.
8. Skip 04 is full now with a dead plant in it disposed by some residents on the same street.
Visit: 1
11.15am
1. Back e-ducting done outside. 19 skip was taken away but ss water tank moved to a temporary place on the roof.
2. Y working on MBR front wall.
3. Sturdym and saiyuki on plastering inner front dining wall.
4. AK working on wet area floor.
5. Bumblebee putting up bricks in courtyard.
6. Bguy cutting previous exposed iron rods in the floor.
7. Tinman mixing cement and sand.
8. Skip 04 is full now with a dead plant in it disposed by some residents on the same street.
Friday, June 10, 2011
Wdy 64 (d74) Floor
Rain: Drizzle for about 20minutes ~12.30pm
Visit: 1
11.45am
1. Storeroom and study floor is done.
2. Working on the wet kitchen floor and MBR floor.
3. SS pipe across the courtyard is done.
4. Got the Tat wall fan 175
Visit: 1
11.45am
1. Storeroom and study floor is done.
2. Working on the wet kitchen floor and MBR floor.
3. SS pipe across the courtyard is done.
4. Got the Tat wall fan 175
Thursday, June 9, 2011
Wdy 63 (d73) "Sar fui" front rc roof
Rain: - (so far at 5.30pm)
Visit: 1
~9am
1. In car, the men can be seen working on top of the front rc roof putting on the "sar fui".
2. Electricians not here yet. Called them later about not needing the additional metal strip for the pendant light in the wet area and about installing the ceiling fan hook the normal way onto the roof beam.
3. Bguy can be seen passing buckets of "sar fui" up to the person on the front rc roof.
4. Was told that a long ss water pipe with a big diameter is on site.
*Have not posted for 9 days so catching up on the 8 back posts today*
Visit: 1
~9am
1. In car, the men can be seen working on top of the front rc roof putting on the "sar fui".
2. Electricians not here yet. Called them later about not needing the additional metal strip for the pendant light in the wet area and about installing the ceiling fan hook the normal way onto the roof beam.
3. Bguy can be seen passing buckets of "sar fui" up to the person on the front rc roof.
4. Was told that a long ss water pipe with a big diameter is on site.
*Have not posted for 9 days so catching up on the 8 back posts today*
Wednesday, June 8, 2011
Wdy 62 (d72) "Sar fui" back rc roof
Rain: Heavy rain around 3.30pm to ?8pm?
Visit: 1
~10.45am
1. Mini sand dune in front of the house. Later was told that this sand is coarse so can not be mixed with the fine sand.
2. All 4 cmen on the back rc roof putting "sar fui" on it.
3. Went in as well.
4. Noticed that the hole for water tank has been created.
5. Had to request one e-connection conduit to be redone.
6. Went to settle the 4th claim at 3pm after which it rained heavily.
7. Decided to just do the normal way of installing the ceiling fan as I was afraid the men would be like tikus baki labu since they do not seem to be in favour of doing it the way I want it to be done.
8. Decided to not add an additional metal to centralise the pendant light in the wet area.
Visit: 1
~10.45am
1. Mini sand dune in front of the house. Later was told that this sand is coarse so can not be mixed with the fine sand.
2. All 4 cmen on the back rc roof putting "sar fui" on it.
3. Went in as well.
4. Noticed that the hole for water tank has been created.
5. Had to request one e-connection conduit to be redone.
6. Went to settle the 4th claim at 3pm after which it rained heavily.
7. Decided to just do the normal way of installing the ceiling fan as I was afraid the men would be like tikus baki labu since they do not seem to be in favour of doing it the way I want it to be done.
8. Decided to not add an additional metal to centralise the pendant light in the wet area.
Tuesday, June 7, 2011
Wdy 61 (d71) Plaster back wall acman
Rain: *no rain*
Visit: 1
~10.15am
1. Look through electrical trunking. I went in after a long time.
2. All 4 cmen at the back, busy plastering the back wall.
3. 19 started work on hacking the back rc roof.
4. Consultation with acman at around 11.30am.
5. Bumblebee working alone to brick up the front of the MBR. Asked him to create 2 holes for the copper piping and water piping which he did on the same day (when we checked the next day).
6. Both side of the external side walls have been plastered and a pipe conduit put in around the e-wires to 18.
7. Received 4th claim.
Visit: 1
~10.15am
1. Look through electrical trunking. I went in after a long time.
2. All 4 cmen at the back, busy plastering the back wall.
3. 19 started work on hacking the back rc roof.
4. Consultation with acman at around 11.30am.
5. Bumblebee working alone to brick up the front of the MBR. Asked him to create 2 holes for the copper piping and water piping which he did on the same day (when we checked the next day).
6. Both side of the external side walls have been plastered and a pipe conduit put in around the e-wires to 18.
7. Received 4th claim.
Monday, June 6, 2011
Wdy 60 (d70) Electricity trunking starts
Rain: *no rain*
Visit: 2
~7.45am
1. Sat in car and noticed that the roof has flashing on 18 side. Checked it out and was told all flashings have been laid but is red in colour.
2. Didnot meet C and confirm that ac not coming today. AC called to arrange to meet tomorrow instead.
~2.45pm
1. Met the 2 electricians and walked through the piping and trunking paths.
2. Met ss grilled man and briefed him on the design. Saw the man while cooking in car.
Visit: 2
~7.45am
1. Sat in car and noticed that the roof has flashing on 18 side. Checked it out and was told all flashings have been laid but is red in colour.
2. Didnot meet C and confirm that ac not coming today. AC called to arrange to meet tomorrow instead.
~2.45pm
1. Met the 2 electricians and walked through the piping and trunking paths.
2. Met ss grilled man and briefed him on the design. Saw the man while cooking in car.
Sunday, June 5, 2011
D69 Rest day (assumed)
Rain: *drizzling early morning, ended by noon)
Visit: 0
1. We assume that there is no work done today.
Visit: 0
1. We assume that there is no work done today.
Saturday, June 4, 2011
Wdy 59 (d68) Plastering MBR conts'
Rain: *nil*
Visit: 1
~9.15am
1. 2/3 roof beams done. One to go.
2. All 4 cmen are lined up in a row on the scafolding working on plastering the MBR wall next to 16.
3. The cross has been plastered.
Visit: 1
~9.15am
1. 2/3 roof beams done. One to go.
2. All 4 cmen are lined up in a row on the scafolding working on plastering the MBR wall next to 16.
3. The cross has been plastered.
Friday, June 3, 2011
Wdy 58 (d67) Plastering highest roof beam
Rain: *drizzling in the evening*
Visit: 2
~8am
1. More Cworkers - saiyuki, sturdy man, Y, AK with Bguy, bumblebee, itinman.
2. Sealing up the joint between the metal deck and the front wall.
3. Going to plaster the highest roof beam.
4. Surprise drop in while passing by to get ac contact. C not going to P this weekend.
~9.45pm
1. Pass by to see the lightings at night.
2. Back lane is dark.
3. Front lane only 18 is well lighted.
Visit: 2
~8am
1. More Cworkers - saiyuki, sturdy man, Y, AK with Bguy, bumblebee, itinman.
2. Sealing up the joint between the metal deck and the front wall.
3. Going to plaster the highest roof beam.
4. Surprise drop in while passing by to get ac contact. C not going to P this weekend.
~9.45pm
1. Pass by to see the lightings at night.
2. Back lane is dark.
3. Front lane only 18 is well lighted.
Thursday, June 2, 2011
Wdy 57 (d66) Plastering conts'
Rain: *no rain*
Visit: 1
~7.30am
1. Was there early. Saw the thin young iman being taken away to join another crew that needs extra hand (the pond in Princess town).
2. Sturdy man still there. Plastering works continue.
3. Waited for C and passed gate design and etc to him.
4. Went to P to get seesee and got lights.
Visit: 1
~7.30am
1. Was there early. Saw the thin young iman being taken away to join another crew that needs extra hand (the pond in Princess town).
2. Sturdy man still there. Plastering works continue.
3. Waited for C and passed gate design and etc to him.
4. Went to P to get seesee and got lights.
Wednesday, June 1, 2011
Wdy 56 (d65) Plastering roof beams
Rain: *no rain*
Visit: 1
8.15am
1. Didn't meet C
2. Noticed a new face on site - a sturdy Cman getting ready to plaster the roof beams.
3. Going to plaster the MBR wall next to the planned dining area.
4. Back to wait for the A-instant water shower heater.
Visit: 1
8.15am
1. Didn't meet C
2. Noticed a new face on site - a sturdy Cman getting ready to plaster the roof beams.
3. Going to plaster the MBR wall next to the planned dining area.
4. Back to wait for the A-instant water shower heater.
Tuesday, May 31, 2011
Wdy 55 (d64) Plastering cont'
Rain: No rain despite thunders from 6am to 8am. Hot and dry day.
Visit: 1
12 noon
1. Was told that 2 more iworkers on site so that means 2c and 6i I think.
2. Work now is concentrated on plastering all the walls that need to be plastered.
3. Wait by car.
Visit: 1
12 noon
1. Was told that 2 more iworkers on site so that means 2c and 6i I think.
2. Work now is concentrated on plastering all the walls that need to be plastered.
3. Wait by car.
Monday, May 30, 2011
Wdy 54 (d63) 3 skylights
Rain: no rain hot day
Visit: 3
8.05am
1. Just missed C, saw him on way there, round the bend.
2. Was told:
- need keys
- skylight will be done today
9.45am
1. Use keys
2. Electricians putting up a temporary stand for the main e-meter
3. E confirm no do ac
4. confirm time for skylight
5. was told that the back window frame is in.
1pm to 2.45pm
1. Specify skylight spots.
2. See them done.
Plastering works continue. 2c, 4i (additional 2). View wire mesh, 7502 (thinker) or 7503 type.
Visit: 3
8.05am
1. Just missed C, saw him on way there, round the bend.
2. Was told:
- need keys
- skylight will be done today
9.45am
1. Use keys
2. Electricians putting up a temporary stand for the main e-meter
3. E confirm no do ac
4. confirm time for skylight
5. was told that the back window frame is in.
1pm to 2.45pm
1. Specify skylight spots.
2. See them done.
Plastering works continue. 2c, 4i (additional 2). View wire mesh, 7502 (thinker) or 7503 type.
Sunday, May 29, 2011
D62 rest day
Rain: no rain
Visit: 1
~5pm
1. Passed through the front after early dinner at fm.
2. No workers around since this is a rest day
3. Front main sdoor has bricks around it.
Visit: 1
~5pm
1. Passed through the front after early dinner at fm.
2. No workers around since this is a rest day
3. Front main sdoor has bricks around it.
Saturday, May 28, 2011
Wdy 53 (d61) Concrete door lintel
Rain: ? afternoon shower?
Visit: 1
7.45am
1. Was told that
- the two louvre window frames have been put in.
- concrete has been casted around the sdoor frames.
- complete putting in the bricks around the front sdoor and back door
2. Waited until 8.45am but still no sign of C so we left. Saw a man walking around as exercise.
Visit: 1
7.45am
1. Was told that
- the two louvre window frames have been put in.
- concrete has been casted around the sdoor frames.
- complete putting in the bricks around the front sdoor and back door
2. Waited until 8.45am but still no sign of C so we left. Saw a man walking around as exercise.
Friday, May 27, 2011
Wdy 52 (d60) connect secdoors con
Rain: Drizzling 8am to 10am
Visit: 1
8am
1. Main purpose is to talk to C about:
- the existing wall is protruding out of the new door frame
-- his solution is to scrap off all the existing plaster on those walls with door frames.
2. Middle sdoor is too low claimed K but C said to do a slopping floor leading to it. (we thought of making a step down in the corridor before it)
3. Work will be done to cast the supporting walls around the sdoors.
4. K asked about the naco windows which C answered.
Work started for 2 months already. 2 more months to go!
Visit: 1
8am
1. Main purpose is to talk to C about:
- the existing wall is protruding out of the new door frame
-- his solution is to scrap off all the existing plaster on those walls with door frames.
2. Middle sdoor is too low claimed K but C said to do a slopping floor leading to it. (we thought of making a step down in the corridor before it)
3. Work will be done to cast the supporting walls around the sdoors.
4. K asked about the naco windows which C answered.
Work started for 2 months already. 2 more months to go!
Thursday, May 26, 2011
Wdy 51 (d59) 3 secdoors
Rain: nil
Visit: 1
8am
1. Meet painter, alman, plumber.
2. Still plastering
3. Secdoor installation 1.15pm to 4.45pm
4. 7 milo ice 2.2 = 15.4 (2cw, 2iw, 1plum, 2doors)
5. Got the rain water pipe direct out but I think he dug through the beams (hhmmm me not happy)
Visit: 1
8am
1. Meet painter, alman, plumber.
2. Still plastering
3. Secdoor installation 1.15pm to 4.45pm
4. 7 milo ice 2.2 = 15.4 (2cw, 2iw, 1plum, 2doors)
5. Got the rain water pipe direct out but I think he dug through the beams (hhmmm me not happy)
Wednesday, May 25, 2011
Wdy 50 (d58) Pressure wproof plaster
Rain: nil I think
Visit: 1
8am
1. Noticed the 18 topfront curve has been plastered
2. Was told that they will put another layer of water proofing on the rc roof
3. Wet kitchen pipe outlet dug
4. Went over the pipe outlet of courtyard punch hole?
5. Plastering wet area
6. Main man feeling the heat until be like me
7. Met bring on additional Wgeyes
8. Colour chart given
9. Went over cnalm route
10. New skip
Visit: 1
8am
1. Noticed the 18 topfront curve has been plastered
2. Was told that they will put another layer of water proofing on the rc roof
3. Wet kitchen pipe outlet dug
4. Went over the pipe outlet of courtyard punch hole?
5. Plastering wet area
6. Main man feeling the heat until be like me
7. Met bring on additional Wgeyes
8. Colour chart given
9. Went over cnalm route
10. New skip
Tuesday, May 24, 2011
Wdy 49 (d57) Water proof rc porch
Rain: 3pm-3.30pm
Visit: 1
8am
1. Noticed that:
- the 18 divider wall has been extended all the way to the front of the rc porch, not plastered yet
- many bags of cement on site
2. Called C to arrange to meet on site (seems like he is too busy to visit today)
3. Update the plumber on the wet area tap change of position and tap of wet kitchen (150mm+..)
4. Water proofing will be done on front rc porch today
5. At the back rc side will 16 have been extended and plastered nicely after it was brought up yesterday
Visit: 1
8am
1. Noticed that:
- the 18 divider wall has been extended all the way to the front of the rc porch, not plastered yet
- many bags of cement on site
2. Called C to arrange to meet on site (seems like he is too busy to visit today)
3. Update the plumber on the wet area tap change of position and tap of wet kitchen (150mm+..)
4. Water proofing will be done on front rc porch today
5. At the back rc side will 16 have been extended and plastered nicely after it was brought up yesterday
Monday, May 23, 2011
Wdy 48 (d56) Lay roof tiles cont'
Rain: Drizzling ~2pm-3pm
Visit: 1
7.30am
1. Noticed that for the part of the roof facing west, the roof tiles have been completed except for a column near 16
2. A few columns near 18 have been done for the part of the roof facing east
3. Cut the roof tiles to fit the final column.
4. Work continues on laying the roof tiles despite slight drizzle
Visit: 1
7.30am
1. Noticed that for the part of the roof facing west, the roof tiles have been completed except for a column near 16
2. A few columns near 18 have been done for the part of the roof facing east
3. Cut the roof tiles to fit the final column.
4. Work continues on laying the roof tiles despite slight drizzle
Sunday, May 22, 2011
D55 Rest day (assume)
Rain: ~11pm
Visit: 0
We assume that this is a rest day for the workers as we did not visit the site at all. Went for lights shopping instead.
Visit: 0
We assume that this is a rest day for the workers as we did not visit the site at all. Went for lights shopping instead.
Saturday, May 21, 2011
Wdy 47 (d54) Roof tiles arrived
Rain: ~6.30pm to 8pm
Visit: 1
11.30am
1. Both electricians were there drilling holes for the electricity wires.
2. All wet works workers were on the roof stacking up the roof tiles.
3. Saw them leaving for lunch at 12pm.
4. G noticed those battens that have been cut and welded look like going rusty so he called and requested C to ensure that these are painted over again.
5. Went to KM to look at tiles and taps.
Visit: 1
11.30am
1. Both electricians were there drilling holes for the electricity wires.
2. All wet works workers were on the roof stacking up the roof tiles.
3. Saw them leaving for lunch at 12pm.
4. G noticed those battens that have been cut and welded look like going rusty so he called and requested C to ensure that these are painted over again.
5. Went to KM to look at tiles and taps.
Friday, May 20, 2011
Wdy 46 (d53) Plaster storeroom
Rain: Short heavy downpour ~2pm to 2.20pm Drizzling 3-4pm
Visit: 1
~4pm
1. Storeroom has been plastered
2. The previous window of the previous living room has been bricked up
3. The ventilation blocks above the previous main door have all been removed
4. Outlet pipe has been embedded into the dry kitchen wall
5. Outlet pipe has been put into the courtyard ground
6. 3 pipes going into the 1st tank now
7. 2 through holes with pipes wall have been created in the back wet cubicles wall
Visit: 1
~4pm
1. Storeroom has been plastered
2. The previous window of the previous living room has been bricked up
3. The ventilation blocks above the previous main door have all been removed
4. Outlet pipe has been embedded into the dry kitchen wall
5. Outlet pipe has been put into the courtyard ground
6. 3 pipes going into the 1st tank now
7. 2 through holes with pipes wall have been created in the back wet cubicles wall
Thursday, May 19, 2011
Wdy 45 (d52) Plaster courtyard
Rain: 7-10pm
Visit:2
1. 7.55am
- complete laying bricks on both sides 16 and 18 of the original ventilation blocks by topping up - I think the brick is pressing on the electric wires.
- started to plaster the external walls of the courtyard.
- drilling the surface of the wet cubicles to roughen the surface
- notice the floor trap of the shower cubicle is in the middle and not near the door
- inform need for computer ducting hole from living to mbr
- notice metal foil flapping in the wind and one part is jutting out
2.30pm
-took photos from 12floor
-roof looks good
2. 3pm
- no plumber
- roofer in the house fastening the metal deck to the battens
- plastering external walls of the courtyard
- notice that the plastic covers have been removed from the 18 top party walls
- notice that flashings have been put on the 18 roof side that sticks to our wall
Visit:2
1. 7.55am
- complete laying bricks on both sides 16 and 18 of the original ventilation blocks by topping up - I think the brick is pressing on the electric wires.
- started to plaster the external walls of the courtyard.
- drilling the surface of the wet cubicles to roughen the surface
- notice the floor trap of the shower cubicle is in the middle and not near the door
- inform need for computer ducting hole from living to mbr
- notice metal foil flapping in the wind and one part is jutting out
2.30pm
-took photos from 12floor
-roof looks good
2. 3pm
- no plumber
- roofer in the house fastening the metal deck to the battens
- plastering external walls of the courtyard
- notice that the plastic covers have been removed from the 18 top party walls
- notice that flashings have been put on the 18 roof side that sticks to our wall
Wednesday, May 18, 2011
Wdy 44 (d51) Plaster all 18 side top
Rain: evening/night
Visit: 1
9.15am to 10.35am
1. C, plumber and electricians already there.
2. No workers in sight because all of them are on the roof plastering 18 side.
3. Inner bricks nearly up.
4. Give high level specs to 2 electricians and plumber. C left before talk with plumber.
5. Was told they use Mega - is it this?
6. Saw that the toilet sewerage pipe has been done - at around 25cm so after tiling so more or less fit 22cm but the plumber does not think it is an issue
7. The overflow tank metal cover is now broken and the tank is now exposed with soil in it. The overflow pipe is blocked by the soil so have to bring this up to C.
8. The ventilation pipe for the toilet has been put in place piercing through the metal deck roof.
9. A drain has been dug in the courtyard area.
Visit: 1
9.15am to 10.35am
1. C, plumber and electricians already there.
2. No workers in sight because all of them are on the roof plastering 18 side.
3. Inner bricks nearly up.
4. Give high level specs to 2 electricians and plumber. C left before talk with plumber.
5. Was told they use Mega - is it this?
6. Saw that the toilet sewerage pipe has been done - at around 25cm so after tiling so more or less fit 22cm but the plumber does not think it is an issue
7. The overflow tank metal cover is now broken and the tank is now exposed with soil in it. The overflow pipe is blocked by the soil so have to bring this up to C.
8. The ventilation pipe for the toilet has been put in place piercing through the metal deck roof.
9. A drain has been dug in the courtyard area.
Tuesday, May 17, 2011
Wdy 43 (d50) Brick mbr top
Rain: afternoon/evening
Visit: 1
8.15am
1. Called C to wait for us (he was at site at the time of the call). All working on a public holiday.
2. Workers are furiously bricking up the top parts of the courtyard and also the MBR.
3. Saw some pipes for sewerage in the back ten.
4. Climbed up the back ten rc roof and took some photos of the roof from the back.
5. Ledges all around for the back window have been casted with wood frames support still in place.
Visit: 1
8.15am
1. Called C to wait for us (he was at site at the time of the call). All working on a public holiday.
2. Workers are furiously bricking up the top parts of the courtyard and also the MBR.
3. Saw some pipes for sewerage in the back ten.
4. Climbed up the back ten rc roof and took some photos of the roof from the back.
5. Ledges all around for the back window have been casted with wood frames support still in place.
Monday, May 16, 2011
Wdy 42 (d49) Plaster 18 side top
Rain: Afternoon
Visit: 1
10am
1. C is not back yet so we went at 10
2. All workers putting paster on 18 side top
3. 2nd room new door is in place and old doorway has been bricked up
4. 3 glass blocks are installed in the storeroom
5. Courtyard vent fan opening has a wooden frame and courtyard top nearly bricked up
Visit: 1
10am
1. C is not back yet so we went at 10
2. All workers putting paster on 18 side top
3. 2nd room new door is in place and old doorway has been bricked up
4. 3 glass blocks are installed in the storeroom
5. Courtyard vent fan opening has a wooden frame and courtyard top nearly bricked up
Sunday, May 15, 2011
D48 rest day
Rain: ~3-5pm
Visit: 1
11am
1. Rest day for the workers
2. New skip 16 has arrived (guess it arrived yesterday after we left)
3. Roof facing east has metal foil on it from 16 to near 18
4. Back door opening last 2 bricks have been cut to the correct size to widen the door opening
5. Wooden frame for the store room ventilation fan has been installed
Visit: 1
11am
1. Rest day for the workers
2. New skip 16 has arrived (guess it arrived yesterday after we left)
3. Roof facing east has metal foil on it from 16 to near 18
4. Back door opening last 2 bricks have been cut to the correct size to widen the door opening
5. Wooden frame for the store room ventilation fan has been installed
Saturday, May 14, 2011
Wrkdy 41 (d47) Metal foil up
Rain: seems likely in the evening, thundering now
Visit: 1
10.30am
1. Went after brunch, lucky to be there at that time when IWK lorry came and the IWK person-in-charged called me to ensure that I am there and asked me to remove the roof lorry parked in the back lane. Saw the desludging in action.
2. The front facing roof has been fully covered with metal deck and they are putting the double sided metal foil up for the front facing roof.
3. Then they started putting up the metal deck for the back portion.
4. Door frame for MBR is in.
5. Putting up the last part of bricks on top of wall divider to 18.
6. Back door way has been cut to bigger size all the way down except for the last brick.
7. Chat to a Mrs L tenant of the row rental costs RM650. Said some bought 260 and do only a little. Said one changed only roof for 20. Said one wanting to sell for 300. Has daughter and son and grandchildren.
8. Y called to tell about courtyard don't over cover with metal deck.
Visit: 1
10.30am
1. Went after brunch, lucky to be there at that time when IWK lorry came and the IWK person-in-charged called me to ensure that I am there and asked me to remove the roof lorry parked in the back lane. Saw the desludging in action.
2. The front facing roof has been fully covered with metal deck and they are putting the double sided metal foil up for the front facing roof.
3. Then they started putting up the metal deck for the back portion.
4. Door frame for MBR is in.
5. Putting up the last part of bricks on top of wall divider to 18.
6. Back door way has been cut to bigger size all the way down except for the last brick.
7. Chat to a Mrs L tenant of the row rental costs RM650. Said some bought 260 and do only a little. Said one changed only roof for 20. Said one wanting to sell for 300. Has daughter and son and grandchildren.
8. Y called to tell about courtyard don't over cover with metal deck.
Friday, May 13, 2011
Wrkdy 40 (d46) Roof truss going up
Rain: nil
Visit: 1
7.25am
1. Went for breakfast at 6.30am and were the first ones to reach the site, just in time to see AK and a thin young iman came in.
2. C then came and we chose the colour of satin leather rather then grey
3. The dividing wall of the storeroom and wet kitchen is up with the metal door frame in place.
4. The new door way of the 2nd room has been created by knocking a hole in the wall but the old doorway has not been bricked up yet.
5. The ventilation bricks on top of the existing door way of the new 2nd room have been removed but not bricked up yet.
6. Still putting up the top of the separator wall of 18.
7. Started putting up the bare brick walls of the living room.
8. Called IWK to come and do desludging.
9. Digging toilet pathways.
Visit: 1
7.25am
1. Went for breakfast at 6.30am and were the first ones to reach the site, just in time to see AK and a thin young iman came in.
2. C then came and we chose the colour of satin leather rather then grey
3. The dividing wall of the storeroom and wet kitchen is up with the metal door frame in place.
4. The new door way of the 2nd room has been created by knocking a hole in the wall but the old doorway has not been bricked up yet.
5. The ventilation bricks on top of the existing door way of the new 2nd room have been removed but not bricked up yet.
6. Still putting up the top of the separator wall of 18.
7. Started putting up the bare brick walls of the living room.
8. Called IWK to come and do desludging.
9. Digging toilet pathways.
Thursday, May 12, 2011
Wrkdy 39 (d45) bricks party wall 18
Rain: light long rain ~ 5pm-8pm
Visit: 1
9.50am
1. Supposed to be a quick see shoot but turned to be a long chatty conversation with one of the two roof installers.
2. Saw the plumber come in.
3. Start to lay bricks top party wall 18.
4. Lined the wash area door way with perforated 90 degree line strips.
5. One mroof installer joining up 3 feet to the existing 20 feet mild steel.
Visit: 1
9.50am
1. Supposed to be a quick see shoot but turned to be a long chatty conversation with one of the two roof installers.
2. Saw the plumber come in.
3. Start to lay bricks top party wall 18.
4. Lined the wash area door way with perforated 90 degree line strips.
5. One mroof installer joining up 3 feet to the existing 20 feet mild steel.
Wednesday, May 11, 2011
Wrkdy 38 (d44) roof truss cont' pwall 16
Rain: short concentrated rain ~ 3pm-4pm
Visit: 1
7.40am
1. Reached there early before C but all 3 workers were already there.
2. C asked to choose windows/doors frame colour. Matt black chosen.
3. Work continued laying bricks for party wall 16
4. Roof truss metal 2mm thickness 2inchx4inch box section
4. At around 9.30am two men came to work on the mild steel roof truss
5. 9.40am secman came to give the quote. More discussion.
6. Discuss with C and decided to switch place of wc and shower. Wc next to 18 instead of shower stall.
Visit: 1
7.40am
1. Reached there early before C but all 3 workers were already there.
2. C asked to choose windows/doors frame colour. Matt black chosen.
3. Work continued laying bricks for party wall 16
4. Roof truss metal 2mm thickness 2inchx4inch box section
4. At around 9.30am two men came to work on the mild steel roof truss
5. 9.40am secman came to give the quote. More discussion.
6. Discuss with C and decided to switch place of wc and shower. Wc next to 18 instead of shower stall.
Tuesday, May 10, 2011
Wrkdy 37 (d43) bricks high up party wall 16
Rain: nil (7 days without a single drop of rain)
Visit: 1
8.10am
1. Did not meet C
2. Bricks for party wall 16 high up.
3. Brick up previous window of wc.
4. Install door frame for store room.
5. Went in to have a look and feel. Wash area felt small. Common area is spacious.
6. Need to change folding doors to open indoor and cover the whole opening framed by concrete pillars.
7. Called secdoor to postpone 16 date delivery because we think it is better to have the roof up before putting in the secdoors.
Visit: 1
8.10am
1. Did not meet C
2. Bricks for party wall 16 high up.
3. Brick up previous window of wc.
4. Install door frame for store room.
5. Went in to have a look and feel. Wash area felt small. Common area is spacious.
6. Need to change folding doors to open indoor and cover the whole opening framed by concrete pillars.
7. Called secdoor to postpone 16 date delivery because we think it is better to have the roof up before putting in the secdoors.
Monday, May 9, 2011
Wrkdy 36 (d42) remove front rc wood support
Rain: nil
Visit: 1
9am
1. Workers removing rc wood support
2. Confirm the size of the door way for the wash area
3. From the photos, I notice for the brick wall in the wash area (party wall to 18), the cement mortar mix is used in abundance in one area acting as the bricks to fill up a large gap.
4. Did not meet C.
Visit: 1
9am
1. Workers removing rc wood support
2. Confirm the size of the door way for the wash area
3. From the photos, I notice for the brick wall in the wash area (party wall to 18), the cement mortar mix is used in abundance in one area acting as the bricks to fill up a large gap.
4. Did not meet C.
Sunday, May 8, 2011
D41 rest day
Rain: nil
Visit: 1
9am
1. No workers on site - rest day.
2. Took aerial photos from 12 floor.
Visit: 1
9am
1. No workers on site - rest day.
2. Took aerial photos from 12 floor.
Saturday, May 7, 2011
Wrkdy 35 (d40) brick laying washarea
Rain: nil
Visit: 1
8am
1. Most party wall done until roof beam
2. Informed AK that the cubicles for wc and shower should be just openings with no lintel across the openings
3. Should be doing wash area bricks today
4. 3 aluminium door frames are there (maybe delivered yesterday)
5. Took aerial photo
Visit: 1
8am
1. Most party wall done until roof beam
2. Informed AK that the cubicles for wc and shower should be just openings with no lintel across the openings
3. Should be doing wash area bricks today
4. 3 aluminium door frames are there (maybe delivered yesterday)
5. Took aerial photo
Friday, May 6, 2011
Wrkdy 34 (d39) cont brick party wall
Rain: nil
Visit: 1
8am
1. Party wall back ten with 16 has been completed with topping up their party wall too.
2. Window of room 2 facing back ten has been bricked up neatly.
3. Party wall room 2 with 16 has been done until roof beam.
4. Party wall dry kitchen with 18 in progress.
5. Removing wood support from roof beam.
6. The bricks are laid very neatly.
7. Selected off white for metal deck.
8. Informed C that the cubicles for wc and shower should be just openings with no lintel across the openings.
Visit: 1
8am
1. Party wall back ten with 16 has been completed with topping up their party wall too.
2. Window of room 2 facing back ten has been bricked up neatly.
3. Party wall room 2 with 16 has been done until roof beam.
4. Party wall dry kitchen with 18 in progress.
5. Removing wood support from roof beam.
6. The bricks are laid very neatly.
7. Selected off white for metal deck.
8. Informed C that the cubicles for wc and shower should be just openings with no lintel across the openings.
Thursday, May 5, 2011
Wrkdy 33 (d38) start brick party wall
Rain: nil
Visit: 1
8am
1. Bricks at back ten wall done half.
2. The gap between 18 and the back ten side party wall has been filled up with bricks.
3. C came at 814. Sending workers to stayover at the princess pond.
Visit: 1
8am
1. Bricks at back ten wall done half.
2. The gap between 18 and the back ten side party wall has been filled up with bricks.
3. C came at 814. Sending workers to stayover at the princess pond.
Wednesday, May 4, 2011
Wrkdy 32 (d37) start brick laying
Rain: nil
Visit: 1
10.30am
1. New skip no 1 is here
2. Started laying bricks at the back wall
3. Asked to confirm size of back door. They just left 3 feet wide so have to demolish some bricks to make it wider.
4. Decided to up the back window by 6inches
Visit: 1
10.30am
1. New skip no 1 is here
2. Started laying bricks at the back wall
3. Asked to confirm size of back door. They just left 3 feet wide so have to demolish some bricks to make it wider.
4. Decided to up the back window by 6inches
Tuesday, May 3, 2011
Wrkdy 31 (d36) bricks arrived
Rain: Heavy rain ~7am to 9am, ~4.30pm to 8pm
Visit: 0
1. Went C office to receive 3 rolls woven
2. Heard ceremonial cut of overhang roof
3. Arrival of 3 pallets of bricks
Visit: 0
1. Went C office to receive 3 rolls woven
2. Heard ceremonial cut of overhang roof
3. Arrival of 3 pallets of bricks
Monday, May 2, 2011
Wrkdy 30 (d35) remove bits front rc roof wood
International Workers Day
Rain: Heavy rain ~6pm-10pm
Visit: 1
10am
1. Went to meet secguy to give him specs
2. Saw some workers working removing the planks from the edge of the front rc roof.
Rain: Heavy rain ~6pm-10pm
Visit: 1
10am
1. Went to meet secguy to give him specs
2. Saw some workers working removing the planks from the edge of the front rc roof.
Sunday, May 1, 2011
Saturday, April 30, 2011
Wrkdy 29 (d33) Cast front rc roof?
Rain: Drizzling ~7.30 to 9am
Visit: 1
~3pm
1. 1passed by the site. No activities can be seen. Felt that there are some iworkers in the house. Tea break perhaps. Has the front rc roof been casted?
Visit: 1
~3pm
1. 1passed by the site. No activities can be seen. Felt that there are some iworkers in the house. Tea break perhaps. Has the front rc roof been casted?
Friday, April 29, 2011
Wrkdy 28 (d32) Wood structure front rc roof
Rain: Drizzling ~7 to 9am
Visit: 2
830am
1. Saw C standing on the wooden frame for the front rc roof
2. Joined him and chat, saw iron frames on the wooden structure
3. N joined in chat
4. Only iworkers on site
5pm
1. Pass by alone, saw new sand and gravel
Visit: 2
830am
1. Saw C standing on the wooden frame for the front rc roof
2. Joined him and chat, saw iron frames on the wooden structure
3. N joined in chat
4. Only iworkers on site
5pm
1. Pass by alone, saw new sand and gravel
Thursday, April 28, 2011
Wrkdy 27 (d31) No visit
Rain: Med ~5-6pm
Visit: 0
1. One called C and got the breakdown = 8x24, 2x10, 2x15, 2x44, 8 = 338 - where did the extra 2 come from? From some other roof beams not mentioned? Reset time to 3pm tomorrow.
Visit: 0
1. One called C and got the breakdown = 8x24, 2x10, 2x15, 2x44, 8 = 338 - where did the extra 2 come from? From some other roof beams not mentioned? Reset time to 3pm tomorrow.
Wednesday, April 27, 2011
Wrkdy 26 (d30) unveil back rc roof
Rain: Heavy rain ~5pm - 6pm
Visit: 1
10.30am
1. One stay car, one went in. First glance - no motorbikes (was told later they were redeployed to Puchong for this day).
2. Only one iworker on site, the rest (3) went to 12th floor to buy tea.
3. Many roof beams are up - highest middle, back room, all are up with wooden frames and scaffolding for support.
4. The wooden frames supporting the back rc roof have all been removed, unveiling the concrete structure.
5. Was told that the plan is to build the wooden frames for the front rc roof and it will be cast this coming Saturday.
6. One email went to me instead but C still called one at about 4.30pm to inform about the 2nd claim. One asked about 340 and C said all around but we still couldn't get it so will ask about this again. Plan to meet up Friday afternoon. One email to the correct place again.
Visit: 1
10.30am
1. One stay car, one went in. First glance - no motorbikes (was told later they were redeployed to Puchong for this day).
2. Only one iworker on site, the rest (3) went to 12th floor to buy tea.
3. Many roof beams are up - highest middle, back room, all are up with wooden frames and scaffolding for support.
4. The wooden frames supporting the back rc roof have all been removed, unveiling the concrete structure.
5. Was told that the plan is to build the wooden frames for the front rc roof and it will be cast this coming Saturday.
6. One email went to me instead but C still called one at about 4.30pm to inform about the 2nd claim. One asked about 340 and C said all around but we still couldn't get it so will ask about this again. Plan to meet up Friday afternoon. One email to the correct place again.
Tuesday, April 26, 2011
Monday, April 25, 2011
Wrkdy 24 (d28) still cast roof beams
Rain: Heavy rain ~3.30pm to 6pm
Visit 1
~9am
1. Many columns are up now including the 9x9 for the front porch next to 18.
2. Some of them just rest on existing walls and frames without footings.
3. The back rc roof still have wooden structure below it to support it.
4. They are working to make more roof beams.
5. Was told the iworkers worked yesterday.
Visit 1
~9am
1. Many columns are up now including the 9x9 for the front porch next to 18.
2. Some of them just rest on existing walls and frames without footings.
3. The back rc roof still have wooden structure below it to support it.
4. They are working to make more roof beams.
5. Was told the iworkers worked yesterday.
Sunday, April 24, 2011
Day 27 Rest day (or not)
Rain: heavy rain ~3.30pm to 5pm
Visit: 0
as it is a rest day on Sunday.
* we were told on Monday (25 April 2011) that the iworkers did work on this day as they prefer to be earning daily wages every day so they came to work on the site and put some wood together to form some structures and made some metal frames.
Visit: 0
as it is a rest day on Sunday.
* we were told on Monday (25 April 2011) that the iworkers did work on this day as they prefer to be earning daily wages every day so they came to work on the site and put some wood together to form some structures and made some metal frames.
Saturday, April 23, 2011
Wrkdy 23 (d26) cast roof beams
Rain: very light rain around 4-5pm (I think)
Visit: 1
8.20am
1. C just left we were told.
2. Some wooden support at the top of the back rc roof have been removed.
3. The two concrete pillars/columns at both sides of the front wall of the house have been casted.
4. Now they are doing the steel frame for the 2 9x9 front rc porch columns.
5. And casting the roof beam alongside 18 for the parapet wall.
6. The courtyard columns have been casted and still in their wooden support frame.
Visit: 1
8.20am
1. C just left we were told.
2. Some wooden support at the top of the back rc roof have been removed.
3. The two concrete pillars/columns at both sides of the front wall of the house have been casted.
4. Now they are doing the steel frame for the 2 9x9 front rc porch columns.
5. And casting the roof beam alongside 18 for the parapet wall.
6. The courtyard columns have been casted and still in their wooden support frame.
Friday, April 22, 2011
Thursday, April 21, 2011
Wrkdy 21 (d24) casting more columns
Rain: Very heavy rain ~3.30pm to 5pm?
Visit: 1
8.54am
1. They have casted more columns and still casting more columns.
2. A worker can be seen drilling the front brick wall to reveal the existing beam.
3. w gave us the water bill (0-6) and AL letter.
4. The back rc roof has been casted and the wooden frame structure is still there for support.
Visit: 1
8.54am
1. They have casted more columns and still casting more columns.
2. A worker can be seen drilling the front brick wall to reveal the existing beam.
3. w gave us the water bill (0-6) and AL letter.
4. The back rc roof has been casted and the wooden frame structure is still there for support.
Wednesday, April 20, 2011
Wrkdy 20 (d23) No visit
Rain:
1. wee hours sounds like heavy downpour 3.30am to 6.30am
2. Light rain in the evening around 4pm to 5pm
Visit: 0
1. Just stay in to recuperate from the heat. Will visit site tomorrow.
1. wee hours sounds like heavy downpour 3.30am to 6.30am
2. Light rain in the evening around 4pm to 5pm
Visit: 0
1. Just stay in to recuperate from the heat. Will visit site tomorrow.
Tuesday, April 19, 2011
Wrkdy 19 (d22) Cast concrete back rc roof
Rain: sudden downpour for about 15mins in the evening.
Visit: 1
9am
1. C called at around 8.15 telling us that the back rc roof will be cast today.
2. Sp climbed up a wooden ladder and view the iron frames in the rc roof.
3. I saw workers pouring one small pail after another. Very tedious and slow. I hope that they can finish casting the whole rc roof in one day.
Visit: 1
9am
1. C called at around 8.15 telling us that the back rc roof will be cast today.
2. Sp climbed up a wooden ladder and view the iron frames in the rc roof.
3. I saw workers pouring one small pail after another. Very tedious and slow. I hope that they can finish casting the whole rc roof in one day.
Monday, April 18, 2011
Sunday, April 17, 2011
Saturday, April 16, 2011
Wrkdy 17 (d19) Ground beam near 18 done
Rain: Light rain half day 8.40am to ~3pm
Visit: 1
8.05am
1. C has left so we did not see him.
2. I went to the back of the house and saw a iworker on top of the wooden structure frame for the rc roof.
3. I was told:
a. Only 4 workers onsite today.
b. Ground beam near 18 is done. Ground beams for washroom are being casted.
c. Two water outlet pipes for floor trap near the garden have been laid.
d. Workers still doing the wooden structure frame for back rc roof.
e. The back rc roof will only be casted next Tue said W (not Mon as told by C).
Visit: 1
8.05am
1. C has left so we did not see him.
2. I went to the back of the house and saw a iworker on top of the wooden structure frame for the rc roof.
3. I was told:
a. Only 4 workers onsite today.
b. Ground beam near 18 is done. Ground beams for washroom are being casted.
c. Two water outlet pipes for floor trap near the garden have been laid.
d. Workers still doing the wooden structure frame for back rc roof.
e. The back rc roof will only be casted next Tue said W (not Mon as told by C).
Friday, April 15, 2011
Wrkdy 16 (d18) No site visit
Rain: Heavy-Med-Light 4.30pm to 6pm
Visit: 0
1. Did not visit site because we visit C at the office to hand over 1st claim amount at 2pm.
2. Brought up full copper wire to C and he said difficult to get full copper so we said we will get our own. C said he will then deduct the cost of the wire from his charges. I wonder how is he going to do that if the wire we buy is much more expensive than what he has factored in. We shall see.
3. Told us that they will mix the concrete and cast the back rc roof next Monday. The wooden frame has to be on for one whole week. He will add extra iron structure to the part where we are going to put the stainless steel water tank.
4. Met the man Mr.L who will be painting our whole house. He knew the previous owner and used to rent the house to store his paint (We did know about the house being used as a paint store).
5. Told C about the decision to have the plaster in between bricks to be flat and not indented.
6. Requested for a quote for full stainless steel pipes installation.
Visit: 0
1. Did not visit site because we visit C at the office to hand over 1st claim amount at 2pm.
2. Brought up full copper wire to C and he said difficult to get full copper so we said we will get our own. C said he will then deduct the cost of the wire from his charges. I wonder how is he going to do that if the wire we buy is much more expensive than what he has factored in. We shall see.
3. Told us that they will mix the concrete and cast the back rc roof next Monday. The wooden frame has to be on for one whole week. He will add extra iron structure to the part where we are going to put the stainless steel water tank.
4. Met the man Mr.L who will be painting our whole house. He knew the previous owner and used to rent the house to store his paint (We did know about the house being used as a paint store).
5. Told C about the decision to have the plaster in between bricks to be flat and not indented.
6. Requested for a quote for full stainless steel pipes installation.
Thursday, April 14, 2011
Wrkdy 15 (d17) Wooden frame for back rc roof
Rain: med-heavy 8.30pm to 9pm
Visit 2
8am
1. We went there directly as we left home only at 7.40am. H arrived 20mins after we did.
2. H showed us the catalog (photocopied) for the vent block.
3. We confirmed the number of stumps (3) listed on the invoice with H.
4. I noticed:
a. 3 iworkers were removing the wooden frame from the 5 columns at the back ten.
b. Only 2 cworkers onsite.
5.30pm
1. Place were locked up and all workers have left for the day.
2. A wooden frame has been built at the back ten for the back rc roof with many supporting wooden beams (our previous roof truss) below it.
Visit 2
8am
1. We went there directly as we left home only at 7.40am. H arrived 20mins after we did.
2. H showed us the catalog (photocopied) for the vent block.
3. We confirmed the number of stumps (3) listed on the invoice with H.
4. I noticed:
a. 3 iworkers were removing the wooden frame from the 5 columns at the back ten.
b. Only 2 cworkers onsite.
5.30pm
1. Place were locked up and all workers have left for the day.
2. A wooden frame has been built at the back ten for the back rc roof with many supporting wooden beams (our previous roof truss) below it.
Wednesday, April 13, 2011
Wrkdy 14 (d16) Cast 5 concrete pillars
Rain: 0
Visit 1
8.05am
1. We went there directly as we woke up at 7.35am. H arrived after we did.
2. H told us that Y called him and both of them went for a site visit yesterday afternoon. Y seems fine with the progress and only emphasized that the pillars should be hidden within the walls.
3. We confirmed the number of footings (13) with H and the places ground beams were required.
4. I noticed:
a. The iron frames for the 5 pillars at the last back ten have been put in place yesterday.
b. 4 of the iron frames have wooden structures ready for concrete to be poured in.
c. Part of 18 zink roof has been removed to accomodate on of the wooden structure of the pillar.
d. W explaining to the iworkers about how the back ten concrete roof is going to be.
5. I was told that:
a. The ground bean alongside 16 has been casted but not the ground beam alongside 18.
b. All 13 footings and stump have been done so 13x450+13x150=7800 is due.
6. From what I am told, the total length of the ground beams add up to 65x2+24x3+20+2x8=238 (x45=10710) feet and as at this morning, 138 feet has been completed so around 60% have been completed (6426).
Postnote: We received the first invoice claim in the evening. 13 footings, 13 columns but only 3 stumps. Ground beam is 226 feet.
Visit 1
8.05am
1. We went there directly as we woke up at 7.35am. H arrived after we did.
2. H told us that Y called him and both of them went for a site visit yesterday afternoon. Y seems fine with the progress and only emphasized that the pillars should be hidden within the walls.
3. We confirmed the number of footings (13) with H and the places ground beams were required.
4. I noticed:
a. The iron frames for the 5 pillars at the last back ten have been put in place yesterday.
b. 4 of the iron frames have wooden structures ready for concrete to be poured in.
c. Part of 18 zink roof has been removed to accomodate on of the wooden structure of the pillar.
d. W explaining to the iworkers about how the back ten concrete roof is going to be.
5. I was told that:
a. The ground bean alongside 16 has been casted but not the ground beam alongside 18.
b. All 13 footings and stump have been done so 13x450+13x150=7800 is due.
6. From what I am told, the total length of the ground beams add up to 65x2+24x3+20+2x8=238 (x45=10710) feet and as at this morning, 138 feet has been completed so around 60% have been completed (6426).
Postnote: We received the first invoice claim in the evening. 13 footings, 13 columns but only 3 stumps. Ground beam is 226 feet.
Tuesday, April 12, 2011
Wrkdy 13 (d15) New batch of workers
Rain:
Med-heavy rain ~6pm to 7.30pm
Visit: 1
~8.20am
1. We went directly to the site as we left home at close to 8am and had to be in a slow moving bumper to bumper traffic once we exited JD.
2. H was already there when we arrived.
3. We noticed new foreign workers (4) on site cutting up plywood with an electrical circle saw.
4. We were told that the other workers were at another site to help out with concrete casting just for this day.
5. Things I noticed:
a. All the 5 holes at the last back ten have been filled up to the brim with soil.
b. A cworker was digging a trench (for ground beam of the parapet wall next to 18).
Postnote: Y and H walked through the site together in the afternoon (H told us the next day).
Med-heavy rain ~6pm to 7.30pm
Visit: 1
~8.20am
1. We went directly to the site as we left home at close to 8am and had to be in a slow moving bumper to bumper traffic once we exited JD.
2. H was already there when we arrived.
3. We noticed new foreign workers (4) on site cutting up plywood with an electrical circle saw.
4. We were told that the other workers were at another site to help out with concrete casting just for this day.
5. Things I noticed:
a. All the 5 holes at the last back ten have been filled up to the brim with soil.
b. A cworker was digging a trench (for ground beam of the parapet wall next to 18).
Postnote: Y and H walked through the site together in the afternoon (H told us the next day).
Monday, April 11, 2011
Wrkdy 12 (d14) Did not visit the site
Rain:
Med-heavy rain ~4.30pm to 5.30pm
Visit: 0
We did not visit the site today as we planned to visit the site early tomorrow morning.
Med-heavy rain ~4.30pm to 5.30pm
Visit: 0
We did not visit the site today as we planned to visit the site early tomorrow morning.
Sunday, April 10, 2011
D13 Rest day
Rain:
Med-heavy rain ~3pm to 4.30pm
Pass by: 1
10:15am
1. The "young man with hp" did lock the gate when he left yesterday.
2. Someone contributed some unwanted vegetation to the skip.
3. It is confirmed that Sunday is a rest day for the workers.
Med-heavy rain ~3pm to 4.30pm
Pass by: 1
10:15am
1. The "young man with hp" did lock the gate when he left yesterday.
2. Someone contributed some unwanted vegetation to the skip.
3. It is confirmed that Sunday is a rest day for the workers.
Saturday, April 9, 2011
Wrkdy 11 (d12) Cast ground beam
Rain:
Light rain ~5pm to 6pm
Visit: 2
1. 8am
a. Workers starting to arrive.
b. Got W to explain about the earth in hole. He said the hole is deep (~3feet) and the ground is hard solid so they cast a layer of concrete deep down and filled the hole with earth on top of the cast concrete. For those holes that are not deep, it will be filled with all concrete.
c. Will dig a trench in the existing bathroom for the ground beam for parapet wall and the concrete for the ground beam will fill up the void.
d. H then arrives with the "young man always on hp" and said about the same thing.
2. 5.50pm
a. Pit stop. All trenches and holes in the back ten have been filled with concrete.
b. The front gate is not closed nor locked so I went down to lock it. As I was closing the gate, a voice from underneath the temporary shed said "don't close it, I am waiting for someone to pick me up". It was the "young man always on hp" and I confirmed with him that he will lock it when he leaves.
c. The ground beam in the garden has been casted.
d. New supply of sand and gravel.
e. Existing skip filled with earth is still there.
Light rain ~5pm to 6pm
Visit: 2
1. 8am
a. Workers starting to arrive.
b. Got W to explain about the earth in hole. He said the hole is deep (~3feet) and the ground is hard solid so they cast a layer of concrete deep down and filled the hole with earth on top of the cast concrete. For those holes that are not deep, it will be filled with all concrete.
c. Will dig a trench in the existing bathroom for the ground beam for parapet wall and the concrete for the ground beam will fill up the void.
d. H then arrives with the "young man always on hp" and said about the same thing.
2. 5.50pm
a. Pit stop. All trenches and holes in the back ten have been filled with concrete.
b. The front gate is not closed nor locked so I went down to lock it. As I was closing the gate, a voice from underneath the temporary shed said "don't close it, I am waiting for someone to pick me up". It was the "young man always on hp" and I confirmed with him that he will lock it when he leaves.
c. The ground beam in the garden has been casted.
d. New supply of sand and gravel.
e. Existing skip filled with earth is still there.
Friday, April 8, 2011
Workday 10 (d11) Dig ground beam
Rain:
Light rain 8.30am to 9.30am
Heavy rain ~7.30pm to 8.30pm
Visit: 2
1. 8.15am
a. One in and out like the Invisible Man. No sight of H.
b. A worker starts to break the ground in the front garden for ground beam.
2. 5.15pm
a. All workers have left.
b. Two holes for footing at the back ten near the original back wall.
c. All 5 holes in the back ten have been casted with concrete.
d. The 3 holes near the drain have earth in them covering the concrete.
e. The middle hole near the drain has bricks lined up around the iron frame for the pillar.
f. A void can be seen under the existing bathroom (cement water container).
g. Trenches for ground beam done at the back ten.
Light rain 8.30am to 9.30am
Heavy rain ~7.30pm to 8.30pm
Visit: 2
1. 8.15am
a. One in and out like the Invisible Man. No sight of H.
b. A worker starts to break the ground in the front garden for ground beam.
2. 5.15pm
a. All workers have left.
b. Two holes for footing at the back ten near the original back wall.
c. All 5 holes in the back ten have been casted with concrete.
d. The 3 holes near the drain have earth in them covering the concrete.
e. The middle hole near the drain has bricks lined up around the iron frame for the pillar.
f. A void can be seen under the existing bathroom (cement water container).
g. Trenches for ground beam done at the back ten.
Thursday, April 7, 2011
Workday 9 (d10) Dig more footing
Rain: Sporadic rain 2.40pm to 3.30pm and 8pm to 8.30pm
Visit: 1
11am
1. More holes were dug at the two sides of the main front wall for footing.
2. Iron frames were being formed for the 3 holes at the back of the house.
3. The concrete poured into the few holes yesterday has set (dried).
Visit: 1
11am
1. More holes were dug at the two sides of the main front wall for footing.
2. Iron frames were being formed for the 3 holes at the back of the house.
3. The concrete poured into the few holes yesterday has set (dried).
Wednesday, April 6, 2011
Workday 8 (d9) Cast footing
Rain: Drizzle 2.50pm to 3.15pm
Visit: 2
1. 8.30am
a. The holes for the footing have been filled with water from the rain from yesterday so the workers are scooping out the water with a pail.
b. Filling up the middle hole at the back and digging a new one beside it nearer to 18.
c. stayed under tree
2. 2.05pm
a. As expected the streng never turned up although a call to y asked us to follow up with the streng.
b. No point waiting so concrete is poured into the holes with ready iron frame in them.
c. 19 and 16 talk
d. H arrived at 2.44pm
e. stayed in car
Visit: 2
1. 8.30am
a. The holes for the footing have been filled with water from the rain from yesterday so the workers are scooping out the water with a pail.
b. Filling up the middle hole at the back and digging a new one beside it nearer to 18.
c. stayed under tree
2. 2.05pm
a. As expected the streng never turned up although a call to y asked us to follow up with the streng.
b. No point waiting so concrete is poured into the holes with ready iron frame in them.
c. 19 and 16 talk
d. H arrived at 2.44pm
e. stayed in car
New hole in the middle of the back |
Iron frame in with the iron for the stump |
Pouring the concrete mix into the hole |
Tuesday, April 5, 2011
Day 8 Sand, iron, cement
Rain: Light rain around 5.30pm to maybe 6.30pm
Visit: 1
We have decided to change our visit schedule to only once per day and only during the morning at 8am since it is much cooler at that time and H is there. So from now on, I will be writing about work done the previous day.
8-9am.
1. Reached there at about 8.05am and saw that a new empty skip is placed outside, alongside the notice board but no workers are at site.
2. Everyone arrived. The hole exposing the clay pipe will be covered since we want windows all the way from the store room till 8 feet.
3. More holes for footing will be dug today.
4. No holes for footing will be dug at the original back wall.
5. First batch of sand, cement, gravel and iron were delivered today.
6. 6 workers onsite, 5y and 1m.
7. Got call at 1145 asking about receipt skip and to arrange for structural engineer visit. Contact direct.
Visit: 1
We have decided to change our visit schedule to only once per day and only during the morning at 8am since it is much cooler at that time and H is there. So from now on, I will be writing about work done the previous day.
8-9am.
1. Reached there at about 8.05am and saw that a new empty skip is placed outside, alongside the notice board but no workers are at site.
2. Everyone arrived. The hole exposing the clay pipe will be covered since we want windows all the way from the store room till 8 feet.
3. More holes for footing will be dug today.
4. No holes for footing will be dug at the original back wall.
5. First batch of sand, cement, gravel and iron were delivered today.
6. 6 workers onsite, 5y and 1m.
7. Got call at 1145 asking about receipt skip and to arrange for structural engineer visit. Contact direct.
Evidence of termites |
Monday, April 4, 2011
Day 7 Front removed and dig footing
Rain: Light rain around 7am to 8am
Visit: 2
1. 12pm
Just passed through the front. Took 2 photos while sitting in the car.
a. Skip 40 is still there.
b. The windows, main door and main door grille have been removed from the front wall.
c. The previous MBR wall has been torn down.
2. 5pm
a. New skip 28 is there.
b. Took photos of the back and front.
c. 2 holes for footing have been dug (in the middle and near 16)
d. The one near 16 is around 2 feet deep. I don't think it can go deeper to 3 feet.
e. The one in the middle has exposed two clay pipes and stopped there at 1 feet deep.
f. One square (near 18) has been marked for the footing.
g. The water supply has been disconnected to the pipes in the place and connected to a temporary tap outside the house. I hope no one helps him/herself to the water from the tap.
Visit: 2
1. 12pm
Just passed through the front. Took 2 photos while sitting in the car.
a. Skip 40 is still there.
b. The windows, main door and main door grille have been removed from the front wall.
c. The previous MBR wall has been torn down.
2. 5pm
a. New skip 28 is there.
b. Took photos of the back and front.
c. 2 holes for footing have been dug (in the middle and near 16)
d. The one near 16 is around 2 feet deep. I don't think it can go deeper to 3 feet.
e. The one in the middle has exposed two clay pipes and stopped there at 1 feet deep.
f. One square (near 18) has been marked for the footing.
g. The water supply has been disconnected to the pipes in the place and connected to a temporary tap outside the house. I hope no one helps him/herself to the water from the tap.
Reading: 36232 |
Sunday, April 3, 2011
Day 6 No visit
Rain: -
Visit: 0
We did not visit the site today because we assume that Sunday is a rest day for the workers and also for the neighbours.
Visit: 0
We did not visit the site today because we assume that Sunday is a rest day for the workers and also for the neighbours.
Saturday, April 2, 2011
Day 5 Back wall and tiles
Rain: very light drizzle around 6am
Visit: 1
1. 5.40pm
T took photos of front and back.
a.From the gate, we looked through the window and saw that the tiles of the toilet and bathroom have been removed.
b. The opening in the window of previous MBR (for aircon) has been nicely boarded up.
c. The whole back wall has been removed with rubble heaped up on the ground.
d. The toilet and bathroom windows, original back door and 3rd room window have been nicely boarded up.
e. The previous skip no. 40 is still there half filled.
I do not think they will work tomorrow as it is a Sunday.
Visit: 1
1. 5.40pm
T took photos of front and back.
a.From the gate, we looked through the window and saw that the tiles of the toilet and bathroom have been removed.
b. The opening in the window of previous MBR (for aircon) has been nicely boarded up.
c. The whole back wall has been removed with rubble heaped up on the ground.
d. The toilet and bathroom windows, original back door and 3rd room window have been nicely boarded up.
e. The previous skip no. 40 is still there half filled.
I do not think they will work tomorrow as it is a Sunday.
Reading: 34190 |
Friday, April 1, 2011
Day 4 knocking down walls
Rain: Medium ~4 to 6pm
Passes: 3
1. 3pm
3 workers were seen to be knocking down walls. Old MBR wall is down. Beam of old MBR is down. Beam of airwell is half down. Bathroom and toilet walls are down.
2. 5.30pm
Drizzling. The skip remover vehicle was in the driveway. Used skip (4) was covered and placed on the road outside. New skip (44) is in the porch.
3. 6.30pm
Rain stopped. Took some photos from outside. Water off.
Passes: 3
1. 3pm
3 workers were seen to be knocking down walls. Old MBR wall is down. Beam of old MBR is down. Beam of airwell is half down. Bathroom and toilet walls are down.
2. 5.30pm
Drizzling. The skip remover vehicle was in the driveway. Used skip (4) was covered and placed on the road outside. New skip (44) is in the porch.
3. 6.30pm
Rain stopped. Took some photos from outside. Water off.
A quaint temporary shelter |
6pm reading: 33784 |
Thursday, March 31, 2011
Day 3 Clear rubble
No rain
Visited twice:
1. 0820 to 1030
a. H took measurement
b. with a coffee shop session to discuss columns, beams 16inches and roof
c. iced coffee, coffee and hot barli kosong 4.10
2. 1738 to 1742
a. ensure the water supply has been turned off
b. take note of work done - the floor has been cleared of rubble
Visited twice:
1. 0820 to 1030
a. H took measurement
b. with a coffee shop session to discuss columns, beams 16inches and roof
c. iced coffee, coffee and hot barli kosong 4.10
2. 1738 to 1742
a. ensure the water supply has been turned off
b. take note of work done - the floor has been cleared of rubble
Skip leaving site at 8am after sokoban |
Wood that was infested by termites |
Morning reading: 3268x |
Evening reading: 33148 |
Wednesday, March 30, 2011
Day 2 early rain
I woke up in the dark, hearing the rain outside. I guess the time to be around 4am? The rain only stopped at around 7.15am. Will the site be all wet and is flooded? I can only wonder.
We did not go to the site in the morning. We only went there at around 4.55pm and saw the workers (4c - 3 workers, 1 is the supervisor - he seemed fresh) preparing to leave. We waited until all of them left before taking photos of the site.
All the roof tiles and roof beams (the entire roof) have been removed. There is a lot of rubble in the last back ten. While taking the photos, I noticed that the skip in front is bigger so they have removed the first skip. Looking at the walls revealed, there is only 1 layer of brick wall between two houses. I wonder should we build our own walls.
Water is flowing in the drain like waterfall. We turned off the water mains but yet the water is still flowing. I can only wonder how much our water bill will be for this month.
We did not go to the site in the morning. We only went there at around 4.55pm and saw the workers (4c - 3 workers, 1 is the supervisor - he seemed fresh) preparing to leave. We waited until all of them left before taking photos of the site.
All the roof tiles and roof beams (the entire roof) have been removed. There is a lot of rubble in the last back ten. While taking the photos, I noticed that the skip in front is bigger so they have removed the first skip. Looking at the walls revealed, there is only 1 layer of brick wall between two houses. I wonder should we build our own walls.
Water is flowing in the drain like waterfall. We turned off the water mains but yet the water is still flowing. I can only wonder how much our water bill will be for this month.
Tuesday, March 29, 2011
Day 1 Half roof taken down
Visited site at around 3pm, half the roof has been taken down.
No rain for the whole day. The morning is cool and the afternoon hot and sunny.
No rain for the whole day. The morning is cool and the afternoon hot and sunny.
Friday, March 25, 2011
Tuesday, March 22, 2011
Monday, January 24, 2011
Wednesday, January 19, 2011
Friday, January 14, 2011
Wednesday, January 12, 2011
Tuesday, January 11, 2011
Monday, January 10, 2011
Friday, January 7, 2011
Spotted
The modern reno look - grey, glass, metal. The grey is too dark for me. I would prefer a brighter colour.
Monday, January 3, 2011
Sunday, January 2, 2011
Spiral stairs
If all is well with the location and place, may consider putting in a spiral staircase up to the top of the car porch after 10 years.
Saturday, January 1, 2011