Tuesday, June 21, 2011

Wdy 73 (d85) wet kit counter

Rain: nil
Visit: 1
8.15am

1. Left house at 7.30am but due to the horrendous traffic, reached there at 8.15am
2. Was told that:
- W was there to supervise M to do all the concrete built-ins, starting with wet kit counter
- An error was spotted for the wet area counter measurement 22' from wall and the bottom is 22' from tile whereas the bottom should be 22' from wall as well - was rectified
- The gate pillars are up
- The water meter house and the trash chute have also taken form in bricks
- Water meter has been moved and all the black pipes are replaced by ss pipes
- Y started doing bricks for the rest of the fence but was stopped by C because the brick pattern is different and the design is with AK
- Tinman broke 16 gate light while breaking the previous near 16 pillar to be shorter (they should have done this earlier when I confirmed with C that the pillar is supposed to be shorter.
- Was shown a wooden cut outs of the letters which are not according to spec at all so was rejected and the specs will be given again tomorrow.
- Painters are onsite and paint cans are there as well.
- Front wall has been white washed and the e-mains wiring has been put back to that wall
- Wet area floor is fully tiled now.
- The button to press ding dong has been installed on the left gate pillar