Wdy 65 (d75) Floor, walls, bricks

Rain: Heavy rain for ~1.5 hours ~4pm to 5.30pm?
Visit: 1
11.15am
1. Back e-ducting done outside. 19 skip was taken away but ss water tank moved to a temporary place on the roof.
2. Y working on MBR front wall.
3. Sturdym and saiyuki on plastering inner front dining wall.
4. AK working on wet area floor.
5. Bumblebee putting up bricks in courtyard.
6. Bguy cutting previous exposed iron rods in the floor.
7. Tinman mixing cement and sand.
8. Skip 04 is full now with a dead plant in it disposed by some residents on the same street.