Monday, June 20, 2011

Wdy 72 (d84) Gate pillars

Rain: nil
Visit: 1
9.15am - 1030am

1. C is already there when we got there since we informed him this morning we will be there at 9am after getting the taps - 2 pillar @ 112 (rrp 160 - previously quoted 91), 1 bib and 3 bib hose @ 62 (rrp 88 - previously quoted 55).
2. Also got a pop waste 39 and a bottle trap 35
3. Went over the sizes of thrash room, wm area, extra bricks area.
4. Went over design of wet area counter and wet kitchen counter.
5. Show the wash basin and kitchen sink.
6. Point out the paint we have chosen from the catalogue.
7. C will ask W to do all the concrete built-ins.
8. Activities on site:
- Break up the near the drain stones to do the gate pillar
- remove more dirt in the garden to make way for concrete before putting in pavers
- start work on building the gate pillars
- painters sanding the bottom white wash paint to paint the real thing
- eman furiously digging for the pipe conduit that they put in earlier in the ground