Rain: nil
Visit:2
8-11.30am
1. Waited for C to talk about solving the water seepage.
2. Fixing the 17 18 gap flow
3. Plastering concrete tank, basin in front
4. Doing the raised up for the back kitchen counter.
5. Emen pulling more wires
6. Youngmen helped out a bit
7. 18 wm moved.
8. Lorry collect waste
4-4.30pm
1. AK went up to roof to solve water seepage
2. cap over mail opening