Wdy 59 (d68) Plastering MBR conts'
Rain:
*nil*
Visit: 1
~9.15am
1. 2/3 roof beams done. One to go.
2. All 4 cmen are lined up in a row on the scafolding working on plastering the MBR wall next to 16.
3. The cross has been plastered.