Thursday, April 7, 2011

Workday 9 (d10) Dig more footing

Rain: Sporadic rain  2.40pm to 3.30pm and 8pm to 8.30pm
Visit: 1


11am
1. More holes were dug at the two sides of the main front wall for footing.
2. Iron frames were being formed for the 3 holes at the back of the house.
3. The concrete poured into the few holes yesterday has set (dried).