Tracking

Daisypath Anniversary tickers

Tuesday, April 12, 2011

Wrkdy 13 (d15) New batch of workers

Rain: 
Med-heavy rain  ~6pm to 7.30pm 

Visit: 1
~8.20am
1. We went directly to the site as we left home at close to 8am and had to be in a slow moving bumper to bumper traffic once we exited JD.
2. H was already there when we arrived.
3. We noticed new foreign workers (4) on site cutting up plywood with an electrical circle saw.
4. We were told that the other workers were at another site to help out with concrete casting just for this day.
5. Things I noticed:
a. All the 5 holes at the last back ten have been filled up to the brim with soil.
b. A cworker was digging a trench (for ground beam of the parapet wall next to 18).

Postnote: Y and H walked through the site together in the afternoon (H told us the next day).

No comments:

Post a Comment