Wednesday, April 13, 2011

Wrkdy 14 (d16) Cast 5 concrete pillars

Rain: 0

Visit 1
8.05am
1. We went there directly as we woke up at 7.35am. H arrived after we did.
2. H told us that Y called him and both of them went for a site visit yesterday afternoon. Y seems fine with the progress and only emphasized that the pillars should be hidden within the walls.
3. We confirmed the number of footings (13) with H and the places ground beams were required.
4. I noticed:
a. The iron frames for the 5 pillars at the last back ten have been put in place yesterday.
b. 4 of the iron frames have wooden structures ready for concrete to be poured in.
c. Part of 18 zink roof has been removed to accomodate on of the wooden structure of the pillar.
d. W explaining to the iworkers about how the back ten concrete roof is going to be.
5. I was told that:
a. The ground bean alongside 16 has been casted but not the ground beam alongside 18.
b. All 13 footings and stump have been done so 13x450+13x150=7800 is due.
6. From what I am told, the total length of the ground beams add up to 65x2+24x3+20+2x8=238 (x45=10710) feet and as at this morning, 138 feet has been completed so around 60% have been completed (6426).

Postnote: We received the first invoice claim in the evening. 13 footings, 13 columns but only 3 stumps. Ground beam is 226 feet.