Workday 10 (d11) Dig ground beam

Rain: 
Light rain  8.30am to 9.30am 
Heavy rain ~7.30pm to 8.30pm
Visit: 2
1. 8.15am
a. One in and out like the Invisible Man. No sight of H.
b. A worker starts to break the ground in the front garden for ground beam.


2. 5.15pm
a. All workers have left.
b. Two holes for footing at the back ten near the original back wall.
c. All 5 holes in the back ten have been casted with concrete.
d. The 3 holes near the drain have earth in them covering the concrete.
e. The middle hole near the drain has bricks lined up around the iron frame for the pillar.
f. A void can be seen under the existing bathroom (cement water container).
g. Trenches for ground beam done at the back ten.