Wednesday, May 18, 2011

Wdy 44 (d51) Plaster all 18 side top

Rain: evening/night
Visit: 1
9.15am to 10.35am
1. C, plumber and electricians already there.
2. No workers in sight because all of them are on the roof plastering 18 side.
3. Inner bricks nearly up.
4. Give high level specs to 2 electricians and plumber. C left before talk with plumber.
5. Was told they use Mega - is it this?
6. Saw that the toilet sewerage pipe has been done - at around 25cm so after tiling so more or less fit 22cm but the plumber does not think it is an issue
7. The overflow tank metal cover is now broken and the tank is now exposed with soil in it. The overflow pipe is blocked by the soil so have to bring this up to C.
8. The ventilation pipe for the toilet has been put in place piercing through the metal deck roof.
9. A drain has been dug in the courtyard area.