Tuesday, May 31, 2011

Wdy 55 (d64) Plastering cont'

Rain: No rain despite thunders from 6am to 8am. Hot and dry day.
Visit: 1
12 noon
1. Was told that 2 more iworkers on site so that means 2c and 6i I think.
2. Work now is concentrated on plastering all the walls that need to be plastered.
3. Wait by car.

Monday, May 30, 2011

Wdy 54 (d63) 3 skylights

Rain: no rain hot day
Visit: 3

8.05am
1. Just missed C, saw him on way there, round the bend.
2. Was told:
- need keys
- skylight will be done today

9.45am
1. Use keys
2. Electricians putting up a temporary stand for the main e-meter
3. E confirm no do ac
4. confirm time for skylight
5. was told that the back window frame is in.

1pm to 2.45pm
1. Specify skylight spots.
2. See them done.

Plastering works continue. 2c, 4i (additional 2). View wire mesh, 7502 (thinker) or 7503 type.

Sunday, May 29, 2011

D62 rest day

Rain: no rain
Visit: 1

~5pm
1. Passed through the front after early dinner at fm.
2. No workers around since this is a rest day
3. Front main sdoor has bricks around it.

Saturday, May 28, 2011

Wdy 53 (d61) Concrete door lintel

Rain: ? afternoon shower?
Visit: 1
7.45am
1. Was told that
- the two louvre window frames have been put in.
- concrete has been casted around the sdoor frames.
- complete putting in the bricks around the front sdoor and back door

2. Waited until 8.45am but still no sign of C so we left. Saw a man walking around as exercise.

Friday, May 27, 2011

Wdy 52 (d60) connect secdoors con

Rain: Drizzling 8am to 10am
Visit: 1
8am
1. Main purpose is to talk to C about:
- the existing wall is protruding out of the new door frame
-- his solution is to scrap off all the existing plaster on those walls with door frames.

2. Middle sdoor is too low claimed K but C said to do a slopping floor leading to it. (we thought of making a step down in the corridor before it)

3. Work will be done to cast the supporting walls around the sdoors.
4. K asked about the naco windows which C answered.

Work started for 2 months already. 2 more months to go!

Thursday, May 26, 2011

Wdy 51 (d59) 3 secdoors

Rain: nil
Visit: 1
8am
1. Meet painter, alman, plumber.
2. Still plastering
3. Secdoor installation 1.15pm to 4.45pm
4. 7 milo ice 2.2 = 15.4 (2cw, 2iw, 1plum, 2doors)
5. Got the rain water pipe direct out but I think he dug through the beams (hhmmm me not happy)

Wednesday, May 25, 2011

Wdy 50 (d58) Pressure wproof plaster

Rain: nil I think
Visit: 1
8am

1. Noticed the 18 topfront curve has been plastered
2. Was told that they will put another layer of water proofing on the rc roof
3. Wet kitchen pipe outlet dug
4. Went over the pipe outlet of courtyard punch hole?
5. Plastering wet area
6. Main man feeling the heat until be like me
7. Met bring on additional Wgeyes
8. Colour chart given
9. Went over cnalm route
10. New skip

Tuesday, May 24, 2011

Wdy 49 (d57) Water proof rc porch

Rain: 3pm-3.30pm
Visit: 1
8am
1. Noticed that:
- the 18 divider wall has been extended all the way to the front of the rc porch, not plastered yet
- many bags of cement on site
2. Called C to arrange to meet on site (seems like he is too busy to visit today)
3. Update the plumber on the wet area tap change of position and tap of wet kitchen (150mm+..)
4. Water proofing will be done on front rc porch today
5. At the back rc side will 16 have been extended and plastered nicely after it was brought up yesterday

Monday, May 23, 2011

Wdy 48 (d56) Lay roof tiles cont'

Rain: Drizzling ~2pm-3pm
Visit: 1
7.30am
1. Noticed that for the part of the roof facing west, the roof tiles have been completed except for a column near 16
2. A few columns near 18 have been done for the part of the roof facing east
3. Cut the roof tiles to fit the final column.
4. Work continues on laying the roof tiles despite slight drizzle

Sunday, May 22, 2011

D55 Rest day (assume)

Rain: ~11pm
Visit: 0

We assume that this is a rest day for the workers as we did not visit the site at all. Went for lights shopping instead.

Saturday, May 21, 2011

Wdy 47 (d54) Roof tiles arrived

Rain: ~6.30pm to 8pm
Visit: 1
11.30am
1. Both electricians were there drilling holes for the electricity wires.
2. All wet works workers were on the roof stacking up the roof tiles.
3. Saw them leaving for lunch at 12pm.
4. G noticed those battens that have been cut and welded look like going rusty so he called and requested C to ensure that these are painted over again.
5. Went to KM to look at tiles and taps.

Friday, May 20, 2011

Wdy 46 (d53) Plaster storeroom

Rain: Short heavy downpour ~2pm to 2.20pm Drizzling 3-4pm
Visit: 1
~4pm
1. Storeroom has been plastered
2. The previous window of the previous living room has been bricked up
3. The ventilation blocks above the previous main door have all been removed
4. Outlet pipe has been embedded into the dry kitchen wall
5. Outlet pipe has been put into the courtyard ground
6. 3 pipes going into the 1st tank now
7. 2 through holes with pipes wall have been created in the back wet cubicles wall

Thursday, May 19, 2011

Wdy 45 (d52) Plaster courtyard

Rain: 7-10pm
Visit:2
1. 7.55am
- complete laying bricks on both sides 16 and 18 of the original ventilation blocks by topping up - I think the brick is pressing on the electric wires.
- started to plaster the external walls of the courtyard.
- drilling the surface of the wet cubicles to roughen the surface
- notice the floor trap of the shower cubicle is in the middle and not near the door
- inform need for computer ducting hole from living to mbr
- notice metal foil flapping in the wind and one part is jutting out

2.30pm
-took photos from 12floor
-roof looks good

2. 3pm
- no plumber
- roofer in the house fastening the metal deck to the battens
- plastering external walls of the courtyard
- notice that the plastic covers have been removed from the 18 top party walls
- notice that flashings have been put on the 18 roof side that sticks to our wall

Wednesday, May 18, 2011

Wdy 44 (d51) Plaster all 18 side top

Rain: evening/night
Visit: 1
9.15am to 10.35am
1. C, plumber and electricians already there.
2. No workers in sight because all of them are on the roof plastering 18 side.
3. Inner bricks nearly up.
4. Give high level specs to 2 electricians and plumber. C left before talk with plumber.
5. Was told they use Mega - is it this?
6. Saw that the toilet sewerage pipe has been done - at around 25cm so after tiling so more or less fit 22cm but the plumber does not think it is an issue
7. The overflow tank metal cover is now broken and the tank is now exposed with soil in it. The overflow pipe is blocked by the soil so have to bring this up to C.
8. The ventilation pipe for the toilet has been put in place piercing through the metal deck roof.
9. A drain has been dug in the courtyard area.

Tuesday, May 17, 2011

Wdy 43 (d50) Brick mbr top

Rain: afternoon/evening
Visit: 1
8.15am
1. Called C to wait for us (he was at site at the time of the call). All working on a public holiday.
2. Workers are furiously bricking up the top parts of the courtyard and also the MBR.
3. Saw some pipes for sewerage in the back ten.
4. Climbed up the back ten rc roof and took some photos of the roof from the back.
5. Ledges all around for the back window have been casted with wood frames support still in place.

Monday, May 16, 2011

Wdy 42 (d49) Plaster 18 side top

Rain: Afternoon
Visit: 1
10am
1. C is not back yet so we went at 10
2. All workers putting paster on 18 side top
3. 2nd room new door is in place and old doorway has been bricked up
4. 3 glass blocks are installed in the storeroom
5. Courtyard vent fan opening has a wooden frame and courtyard top nearly bricked up

Sunday, May 15, 2011

D48 rest day

Rain: ~3-5pm
Visit: 1
11am
1. Rest day for the workers
2. New skip 16 has arrived (guess it arrived yesterday after we left)
3. Roof facing east has metal foil on it from 16 to near 18
4. Back door opening last 2 bricks have been cut to the correct size to widen the door opening
5. Wooden frame for the store room ventilation fan has been installed

Saturday, May 14, 2011

Wrkdy 41 (d47) Metal foil up

Rain: seems likely in the evening, thundering now
Visit: 1
10.30am
1. Went after brunch, lucky to be there at that time when IWK lorry came and the IWK person-in-charged called me to ensure that I am there and asked me to remove the roof lorry parked in the back lane. Saw the desludging in action.
2. The front facing roof has been fully covered with metal deck and they are putting the double sided metal foil up for the front facing roof.
3. Then they started putting up the metal deck for the back portion.
4. Door frame for MBR is in.
5. Putting up the last part of bricks on top of wall divider to 18.
6. Back door way has been cut to bigger size all the way down except for the last brick.
7. Chat to a Mrs L tenant of the row rental costs RM650. Said some bought 260 and do only a little. Said one changed only roof for 20. Said one wanting to sell for 300. Has daughter and son and grandchildren.
8. Y called to tell about courtyard don't over cover with metal deck.

Friday, May 13, 2011

Wrkdy 40 (d46) Roof truss going up

Rain: nil
Visit: 1
7.25am
1. Went for breakfast at 6.30am and were the first ones to reach the site, just in time to see AK and a thin young iman came in.
2. C then came and we chose the colour of satin leather rather then grey
3. The dividing wall of the storeroom and wet kitchen is up with the metal door frame in place.
4. The new door way of the 2nd room has been created by knocking a hole in the wall but the old doorway has not been bricked up yet.
5. The ventilation bricks on top of the existing door way of the new 2nd room have been removed but not bricked up yet.
6. Still putting up the top of the separator wall of 18.
7. Started putting up the bare brick walls of the living room.
8. Called IWK to come and do desludging.
9. Digging toilet pathways.

Thursday, May 12, 2011

Wrkdy 39 (d45) bricks party wall 18

Rain: light long rain ~ 5pm-8pm
Visit: 1
9.50am
1. Supposed to be a quick see shoot but turned to be a long chatty conversation with one of the two roof installers.
2. Saw the plumber come in.
3. Start to lay bricks top party wall 18.
4. Lined the wash area door way with perforated 90 degree line strips.
5. One mroof installer joining up 3 feet to the existing 20 feet mild steel.

Wednesday, May 11, 2011

Wrkdy 38 (d44) roof truss cont' pwall 16

Rain: short concentrated rain ~ 3pm-4pm
Visit: 1
7.40am
1. Reached there early before C but all 3 workers were already there.
2. C asked to choose windows/doors frame colour. Matt black chosen.
3. Work continued laying bricks for party wall 16
4. Roof truss metal 2mm thickness 2inchx4inch box section
4. At around 9.30am two men came to work on the mild steel roof truss
5. 9.40am secman came to give the quote. More discussion.
6. Discuss with C and decided to switch place of wc and shower. Wc next to 18 instead of shower stall.

Tuesday, May 10, 2011

Wrkdy 37 (d43) bricks high up party wall 16

Rain: nil (7 days without a single drop of rain)
Visit: 1
8.10am
1. Did not meet C
2. Bricks for party wall 16 high up.
3. Brick up previous window of wc.
4. Install door frame for store room.
5. Went in to have a look and feel. Wash area felt small. Common area is spacious.
6. Need to change folding doors to open indoor and cover the whole opening framed by concrete pillars.
7. Called secdoor to postpone 16 date delivery because we think it is better to have the roof up before putting in the secdoors.

Monday, May 9, 2011

Wrkdy 36 (d42) remove front rc wood support

Rain: nil
Visit: 1
9am
1. Workers removing rc wood support
2. Confirm the size of the door way for the wash area
3. From the photos, I notice for the brick wall in the wash area (party wall to 18), the cement mortar mix is used in abundance in one area acting as the bricks to fill up a large gap.
4. Did not meet C.

Sunday, May 8, 2011

D41 rest day

Rain: nil
Visit: 1
9am
1. No workers on site - rest day.
2. Took aerial photos from 12 floor.

Saturday, May 7, 2011

Wrkdy 35 (d40) brick laying washarea

Rain: nil
Visit: 1
8am
1. Most party wall done until roof beam
2. Informed AK that the cubicles for wc and shower should be just openings with no lintel across the openings
3. Should be doing wash area bricks today
4. 3 aluminium door frames are there (maybe delivered yesterday)
5. Took aerial photo

Friday, May 6, 2011

Wrkdy 34 (d39) cont brick party wall

Rain: nil
Visit: 1
8am
1. Party wall back ten with 16 has been completed with topping up their party wall too.
2. Window of room 2 facing back ten has been bricked up neatly.
3. Party wall room 2 with 16 has been done until roof beam.
4. Party wall dry kitchen with 18 in progress.
5. Removing wood support from roof beam.
6. The bricks are laid very neatly.
7. Selected off white for metal deck.
8. Informed C that the cubicles for wc and shower should be just openings with no lintel across the openings.

Thursday, May 5, 2011

Wrkdy 33 (d38) start brick party wall

Rain: nil
Visit: 1
8am
1. Bricks at back ten wall done half.
2. The gap between 18 and the back ten side party wall has been filled up with bricks.
3. C came at 814. Sending workers to stayover at the princess pond.

Wednesday, May 4, 2011

Wrkdy 32 (d37) start brick laying

Rain: nil
Visit: 1
10.30am
1. New skip no 1 is here
2. Started laying bricks at the back wall
3. Asked to confirm size of back door. They just left 3 feet wide so have to demolish some bricks to make it wider.
4. Decided to up the back window by 6inches

Tuesday, May 3, 2011

Wrkdy 31 (d36) bricks arrived

Rain: Heavy rain ~7am to 9am, ~4.30pm to 8pm
Visit: 0
1. Went C office to receive 3 rolls woven
2. Heard ceremonial cut of overhang roof
3. Arrival of 3 pallets of bricks

Monday, May 2, 2011

Wrkdy 30 (d35) remove bits front rc roof wood

International Workers Day
Rain: Heavy rain ~6pm-10pm
Visit: 1
10am
1. Went to meet secguy to give him specs
2. Saw some workers working removing the planks from the edge of the front rc roof.

Sunday, May 1, 2011

D34 Rest day

Rain: ~7pm to 11.30pm
Visit: 1
One pass by and did not see anyone at work.