Tracking

Daisypath Anniversary tickers

Tuesday, June 7, 2011

Wdy 61 (d71) Plaster back wall acman

Rain: *no rain*
Visit: 1
~10.15am
1. Look through electrical trunking. I went in after a long time.
2. All 4 cmen at the back, busy plastering the back wall.
3. 19 started work on hacking the back rc roof.
4. Consultation with acman at around 11.30am.
5. Bumblebee working alone to brick up the front of the MBR. Asked him to create 2 holes for the copper piping and water piping which he did on the same day (when we checked the next day).
6. Both side of the external side walls have been plastered and a pipe conduit put in around the e-wires to 18.
7. Received 4th claim.

No comments:

Post a Comment