Monday, April 4, 2011

Day 7 Front removed and dig footing

Rain: Light rain around 7am to 8am
Visit: 2
1. 12pm
Just passed through the front. Took 2 photos while sitting in the car.
a. Skip 40 is still there.
b. The windows, main door and main door grille have been removed from the front wall.
c. The previous MBR wall has been torn down.

2. 5pm
a. New skip 28 is there.
b. Took photos of the back and front.
c. 2 holes for footing have been dug (in the middle and near 16)
d. The one near 16 is around 2 feet deep. I don't think it can go deeper to 3 feet.
e. The one in the middle has exposed two clay pipes and stopped there at 1 feet deep.
f. One square (near 18) has been marked for the footing.
g. The water supply has been disconnected to the pipes in the place and connected to a temporary tap outside the house. I hope no one helps him/herself to the water from the tap.