Sunday, July 31, 2011

D125 Halo come visiting

Drizzling ~9am to 10am

Visit:1

~10.30am to 1.45pm

- Rest and relax
- 1 visitor at 1pm

Saturday, July 30, 2011

Wdy 98 (d124) Wire mesh grill done

Raining heavily 8am - 10am
Visit: 2

1. 8am-2pm
- touch up gate grey and back grill grey
- put in the wire mesh grill (looks good as per design)

2. 9.45pm
- just pass by to view the lighting (took photos)

Friday, July 29, 2011

D123 11 to 8

Raining 5am? - 9am

Visit: 1 (11am to 8pm)

*List is not comprehensive*
1. Sweep floor
2. Mop mbr floor
3. Wipe shower wall tiles
4. Wash hand basin
5. Most importantly to observe the lights through tofu grilled at night

Thursday, July 28, 2011

Wdy 97 (d122) Vent block done, ac

No rain
Visit: whole day (7.45am to 5pm)

1. Ac installed 10-12 1850
2. Vent block wall done
3. 3 tebu x 1.8

Wednesday, July 27, 2011

Wdy 96 (d121) Vent block

Rain: drizzle 2pm-4pm?

Visit: whole day 7.45am - 5.30pm

1. Putting in the vent block wall by W and AK

17 bricks x height 14 bricks (today did till 8 bricks height)

Tuesday, July 26, 2011

D120 Door stoppers

No rain
Visit: 1

~3.30pm to 4.45pm

1. Stick back npaper to mbdwdw
2. Put a screw on 2 door stoppers with hook (11 each)
3. Remove a little more dfsh

Monday, July 25, 2011

D119 Polish frank

No rain
Visit: 1

3.50pm-4.30pm (40mins - before early dinner)

1. Nap
2. Polish frank
3. Scoop up dfsh

Sunday, July 24, 2011

D118 Clean frank

Slight drizzle while we were there.
Visit: 1

11am-1.30pm (2.5hrs)

1. Sudoku medium hit snag
2. Scoop up more dfsh
3. Clean the frank

Saturday, July 23, 2011

D117 Keladi bunting

No rain
Visit: 1

9.30am-10.30am (1hr)
1. Scoop up the floating and sinking fsh.
2. Put in keladi bunting
3. Put in a turf of tiny leaves patch.

Friday, July 22, 2011

D116 Drained fishes

No rain
Visit: 1

11.30am - 3.30pm

1. Wipe lourve glass
2. Wipe wet kitchen floor trap
3. Put in dfish (2)

Thursday, July 21, 2011

D115 Change water

12 noon -1pm Drizzle
Visit: 1

1pm-3pm (between no1 and m)

1. Change water

Wednesday, July 20, 2011

D114 Stops 2

No rain
Visit: 2

8.15am-9.20am
1. Wipe floor trap with brasso


4pm-4.50pm
1. Air the place

Tuesday, July 19, 2011

Monday, July 18, 2011

Wdy 95 (d112) assortment work

No rain
Visit: 2

8am-11.15am
1. C came with 2 men to cut the drainage passage for the folding door and put in the 2 septic tanks covers.
2. Alpha service man exchange the hose (said the no hole one is a dummy set) and put in a new screw to fasten the cover.

1pm-3.45pm
1. Vin Art 2 men tore off the wrongly pasted sheet and put in a new one on the outer (right side)
2. Left the plastic? ridges for us to put in ourselves when the door is dried
3. Asked for lighter (dunno why) - later they went out and bought one.

*16 is back finally from M after visiting her dai kor.

Sunday, July 17, 2011

D111 short visit

No rain
Visit: 1

1. Drop by around 11.30am to spray water on the pavers.

Saturday, July 16, 2011

D110 1st night visit

No rain
Visit: 2

1. Around 1030am to turn off the vent fans.
2. Around 8.45pm to see how the lights look like in the dark.

Friday, July 15, 2011

Wdy 94 (d109) Painters touch up 1-2 hours

Raining since wee hours.
Visit: 1

8am-1030am
1. 2 painters touch up paint here and there. Left at 1030 followed by us. C couldn't make it.

Thursday, July 14, 2011

Wdy 93 (d108) Sweep, mop, varnish whole floor

No rain?
Visit: 1 (whole day for one)

1. 2 painters sweep, mop and varnish the floors of the whole house. So quick. They left at about 1630.

2. 1030-1600 not around left for meetup execs.

Wednesday, July 13, 2011

D107 Rest day by us

No rain - hazy
Visit 1
4.30pm - 5.15pm

1. Water the sand
2. Put in abate (day 2 of soaking)
3. Remove boxes and plastic bags
4. Wipe debris off lower sockets

Tuesday, July 12, 2011

Wdy 92 (d106) Touchup, glass doors

No rain
Visit: whole day (9.30am to 4.30pm)

1. Got call from painter asking us to go there at 9 so reach there 9.30am
2. One eman finish up the work, putting up 2 lights front 3 feet, put on two eplugs for back 2 vent fans, connect the shower, change front porch lights to yellow and remove cover.
3. Vin art came to install 2 glass doors for the 2 cubicles.
4. No water coming out from shower so called plumber who came and discover the shower hose is faulty no hole in it.
5. Called C to pick up the scaffolding and he sent W to pick it up about 20? 30? mins from our call
6. Painter clean up the sec doors frame


**** Work on 18 - Man came to do something to the drain so the water from 19 does not flow onto the driveway.
- Painter sweep and varnish the pebblewash

Monday, July 11, 2011

Wdy 91 (d105) Vent fan shower wfill

No rain
Visit: whole day

1015am
1. Both emen at site when we arrived with C after getting the frightcall.
2. Back to get all things
3. wash tank away 250gallons wtr
4. Big and small in
5. Manage to get small into 103cm (after requesting and changing my request)
6. Pman connected shower, 3 taps and 1 bottle trap
7. Lights almost done
8. All 3 parties got the forms

Sunday, July 10, 2011

D104 Checkup after rain

Rain: 11am - 3pm
Visit: 1

~4.30pm
1. Went in to look at the effect of rain
2. Water through the folding door
3. Water line on the pavers sand

Saturday, July 9, 2011

D103 Night lights

Backdated - post date: Sunday 10 July 2011
No rain
Visit: 2

10.20am - 11am
1. Got forms from pplhky
2. pplhky took photos

~8.30pm
1. Took photos of front and back lights on

Friday, July 8, 2011

Wdy 90 (d102) Autoarm, lights

Backdated - post date: Sunday 10 July 2011

Intermittent drizzle
Visit: 2 (actually whole day we were onsite except for 1 break to str)

8.20am - 2pm

1. 2 painters were waiting
2. Touch up and painted gate pillars tungsten (a tinge of grey only)
3. OmL paint pink
4. 1 eman put in lights
5. Bmmg close up the ends of metal roof truss - can't do anything about the part cut by plumber

3pm - 5pm

1. Painters remove all their things
2. Metal cover back door in

Thursday, July 7, 2011

Wdy 89 (d101) Last wetworks day

Backdated - post date: Sunday 10 July 2011
Cloudy
Visit: 2

7.55am - 1pm
1. Touching up plastering here and there
2. Token appreciation 50x2
3. Painters at work - black downpipes
4. 2 Eman at work
5. Decide to paint the cement rendered front fencing tungsten grey

3pm-5pm
1. Gate, back window grilles and trashchute door

Wednesday, July 6, 2011

Wdy 88 (d100) Doors in

Backdated - post date: Sunday 10 July 2011

Bits of rain
Visit: 3

7.45am - 10am
1. 2 men came and installed the doors and door knobs and fascia board (18) - signs of termites
2. AK and Y plastered up the external gate arms
3. AK put in red bricks for external front walkway
4. Emen relay w

11am - 1 pm
1. Door block not suitable to be installed

3.30pm - 5pm
1. Bboy came and helped move unrequired things onto lorry

*** pebble driveway was washed with acid today

Tuesday, July 5, 2011

Wdy 87 (d99) wgone wc in

Backdated - post date: Sunday 10 July 2011

No rain
Visit: 1 (8am - 6pm)

1. Brought the toilet bowl and taps
2. Discover
- percussion hammer gone
- 2 septic tank covers gone
- wgone
3. One e-man came to ensure 1 point has e for usage
4. Toilet bowl and internal taps and bottle trap in
5. Fast unpainted grilles in at 5pm
6. C brought 3 doors in
It is the effort mourned

*** Y, AK and bboy only worked on 18 pebble wash putting in the cement mix with pebbles and then wash the cement away

Monday, July 4, 2011

Wdy 86 (d98) Water tank connected

Backdated - post date: Sunday 10 July 2011

No rain
Visit: 2 (at ef3oh)

8am - 1pm
1. Waiting with the taps but soon see that tap work will not be today so left for lunch.
2. was told that tinman quit
3. Pipe work only
4. Glass folding door men came to look at fixing the gap and the bottom part that scratches the floor.

5pm
1. Noticed that the w-meter was moved and the elbow was encased in concrete so we removed the concrete.

*** Don't think any wet work was done on the place as both men were working on the concrete for 18 driveway

Sunday, July 3, 2011

Wdy 85 (d97) Clean up

Backdated - post date: Sunday 10 July 2011

No rain
Visit: 2 (at ef3oh)

10.30am?
1. Pipe work
2. C's son and sman "clean" the floor - remove everything from the floor of the house, sweep and wash the floor.

5pm?
1. C's son (new red car bka) and sman waiting outside the house for lorry to remove more things.

*** Sman use the percussion hammer to hack the whole of 18 concrete driveway and lorry AC removed the debris

Saturday, July 2, 2011

Wdy 84 (d96) Concrete front driveway done

Backdated - post date: Sunday 10 July 2011
No rain
Visit 2 (at ef3oh)

8.30am - 11am
1. One watch marathon, one went look see
2. Folding door top large gap
3. Tinman MIA so only 2 fifties Y and AK

12noon
1. Visit metal works workshop to see gate. No need middle bar.

5pm
1. Concrete front part of driveway done
2. E-meter moved to front wall
3. Pipe work on fencewall near 18 done with gap for wtrfltr

*** No work done on 18 driveway. Only half of the driveway has its top layer of concrete removed

Friday, July 1, 2011

Wdy 83 (d95) Folding door in

Backdated - post date: Sunday 10 July 2011
No rain
Visit: 1 (8am-10.30am)

1. Pavers for driveway
2. E men putting in switches and etc
3. A men continue laying ducting
4. Drain covered with concrete slabs
5. Install folding door and put in glass for the louvers windows

*** Tinman was tasked to use the e-cutter to cut a line between 18 tiled driveway and 18 concrete driveway in order to do the pebble wash and then break the concrete driveway.